UPDATED: CAPACITY REDUCTION Southwest area (Updated: 7/24/25)
ANR Pipeline Company 2mo ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP
006958581
TSP Name
ANR Pipeline Company
Notice Type Desc
Plnd Outage
Posting Date/Time
07/24/2025 8:45 am
Notice Effective Date/Time
07/24/2025 8:45 am
Notice End Date/Time
08/01/2025 8:59 am
Notice ID
12474
Notice Status Desc
Supersede
Prior Notice
12454
Reqrd Rsp
5
Rsp Date/Time
Subject
UPDATED: CAPACITY REDUCTION Southwest area (Updated: 7/24/25)
Notice Text
UPDATED: CAPACITY REDUCTION Southwest area (Updated: 7/24/25)
Since the last posting, ANR has extended maintenance in the Southwest area. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. As a result, capacity will be reduced as follows:
7/21 - 7/31 (previously 7/27) EG Hill Northbound (LOC #226643): 59 MMcf/d (leaving 156 MMcf/d)
Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
21% - Based on the Current Contracted MDQ
7/21 - 7/31 (previously 7/27) Mooreland Northbound (LOC #9505448): 56 MMcf/d (leaving 150 MMcf/d)
Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
26% - Based on the Current Contracted MDQ
7/21 - 7/31 (previously 7/27) Custer Northbound (LOC #226644): 15 MMcf/d (leaving 25 MMcf/d)
Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
36% - Based on the Current Contracted MDQ
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.
Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267
006958581
TSP Name
ANR Pipeline Company
Notice Type Desc
Plnd Outage
Posting Date/Time
07/24/2025 8:45 am
Notice Effective Date/Time
07/24/2025 8:45 am
Notice End Date/Time
08/01/2025 8:59 am
Notice ID
12474
Notice Status Desc
Supersede
Prior Notice
12454
Reqrd Rsp
5
Rsp Date/Time
Subject
UPDATED: CAPACITY REDUCTION Southwest area (Updated: 7/24/25)
Notice Text
UPDATED: CAPACITY REDUCTION Southwest area (Updated: 7/24/25)
Since the last posting, ANR has extended maintenance in the Southwest area. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. As a result, capacity will be reduced as follows:
7/21 - 7/31 (previously 7/27) EG Hill Northbound (LOC #226643): 59 MMcf/d (leaving 156 MMcf/d)
Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
21% - Based on the Current Contracted MDQ
7/21 - 7/31 (previously 7/27) Mooreland Northbound (LOC #9505448): 56 MMcf/d (leaving 150 MMcf/d)
Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
26% - Based on the Current Contracted MDQ
7/21 - 7/31 (previously 7/27) Custer Northbound (LOC #226644): 15 MMcf/d (leaving 25 MMcf/d)
Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
36% - Based on the Current Contracted MDQ
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.
Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267
TSP
006958581
TSP Name
ANR Pipeline Company
Notice Type Desc
Plnd Outage
Posting Date/Time
07/24/2025 8:45 am
Notice Effective Date/Time
07/24/2025 8:45 am
Notice End Date/Time
08/01/2025 8:59 am
Notice ID
12474
Notice Status Desc
Supersede
Prior Notice
12454
Reqrd Rsp
5
Rsp Date/Time
Subject
UPDATED: CAPACITY REDUCTION Southwest area (Updated: 7/24/25)
Notice Text
UPDATED: CAPACITY REDUCTION Southwest area (Updated: 7/24/25)
Since the last posting, ANR has extended maintenance in the Southwest area. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. As a result, capacity will be reduced as follows:
7/21 - 7/31 (previously 7/27) EG Hill Northbound (LOC #226643): 59 MMcf/d (leaving 156 MMcf/d)
Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
21% - Based on the Current Contracted MDQ
7/21 - 7/31 (previously 7/27) Mooreland Northbound (LOC #9505448): 56 MMcf/d (leaving 150 MMcf/d)
Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
26% - Based on the Current Contracted MDQ
7/21 - 7/31 (previously 7/27) Custer Northbound (LOC #226644): 15 MMcf/d (leaving 25 MMcf/d)
Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
36% - Based on the Current Contracted MDQ
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.
Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267
006958581
TSP Name
ANR Pipeline Company
Notice Type Desc
Plnd Outage
Posting Date/Time
07/24/2025 8:45 am
Notice Effective Date/Time
07/24/2025 8:45 am
Notice End Date/Time
08/01/2025 8:59 am
Notice ID
12474
Notice Status Desc
Supersede
Prior Notice
12454
Reqrd Rsp
5
Rsp Date/Time
Subject
UPDATED: CAPACITY REDUCTION Southwest area (Updated: 7/24/25)
Notice Text
UPDATED: CAPACITY REDUCTION Southwest area (Updated: 7/24/25)
Since the last posting, ANR has extended maintenance in the Southwest area. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. As a result, capacity will be reduced as follows:
7/21 - 7/31 (previously 7/27) EG Hill Northbound (LOC #226643): 59 MMcf/d (leaving 156 MMcf/d)
Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
21% - Based on the Current Contracted MDQ
7/21 - 7/31 (previously 7/27) Mooreland Northbound (LOC #9505448): 56 MMcf/d (leaving 150 MMcf/d)
Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
26% - Based on the Current Contracted MDQ
7/21 - 7/31 (previously 7/27) Custer Northbound (LOC #226644): 15 MMcf/d (leaving 25 MMcf/d)
Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
36% - Based on the Current Contracted MDQ
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.
Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267