UPDATED: CAPACITY REDUCTION - Southeast Area - Patterson Compressor Station (Updated: 8/27/25)
ANR Pipeline Company 1mo ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP
006958581
TSP Name
ANR Pipeline Company
Notice Type Desc
Plnd Outage
Posting Date/Time
08/27/2025 9:35 am
Notice Effective Date/Time
08/27/2025 9:35 am
Notice End Date/Time
09/02/2025 8:59 am
Notice ID
12543
Notice Status Desc
Supersede
Prior Notice
12531
Reqrd Rsp
5
Rsp Date/Time
Subject
UPDATED: CAPACITY REDUCTION - Southeast Area - Patterson Compressor Station (Updated: 8/27/25)
Notice Text
UPDATED: CAPACITY REDUCTION - Southeast Area - Patterson Compressor Station (Updated: 8/27/25)
ANR has revised the capacity impact for St. Landry/FL Int (LOC #322625) for the Patterson Compression Station maintenance in the Southeast Area. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. As a result, capacity will be reduced as follows:
8/27 - 9/1:
Patterson/Trunkline (LOC #40317): 94 MMcf/d (leaving 0 MMcf/d)
Patterson to Col Gulf (LOC #43613): 143 MMcf/d (leaving 0 MMcf/d)
Riverway (To Bridgeline) (LOC #42593): 90 MMcf/d (leaving 170 MMcf/d)
Avalon (LOC #38295): 90 MMcf/d (leaving 20 MMcf/d)
Shadyside/Sonat (Del) (LOC #10369): 202 MMcf/d (leaving 285 MMcf/d)
Shadyside/TGP (Del) (LOC #467240): 413 MMcf/d (leaving 30 MMcf/d)
St. Landry/FL Int (LOC #322625): Firm Primary only (previously shut in)
Weeks ISLA/LIG PL (LOC #233620): 298 MMcf/d (leaving 12 MMcf/d)
Opelousas (LOC #10111): 65 MMcf/d (leaving 15 MMcf/d)
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.
Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267
006958581
TSP Name
ANR Pipeline Company
Notice Type Desc
Plnd Outage
Posting Date/Time
08/27/2025 9:35 am
Notice Effective Date/Time
08/27/2025 9:35 am
Notice End Date/Time
09/02/2025 8:59 am
Notice ID
12543
Notice Status Desc
Supersede
Prior Notice
12531
Reqrd Rsp
5
Rsp Date/Time
Subject
UPDATED: CAPACITY REDUCTION - Southeast Area - Patterson Compressor Station (Updated: 8/27/25)
Notice Text
UPDATED: CAPACITY REDUCTION - Southeast Area - Patterson Compressor Station (Updated: 8/27/25)
ANR has revised the capacity impact for St. Landry/FL Int (LOC #322625) for the Patterson Compression Station maintenance in the Southeast Area. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. As a result, capacity will be reduced as follows:
8/27 - 9/1:
Patterson/Trunkline (LOC #40317): 94 MMcf/d (leaving 0 MMcf/d)
Patterson to Col Gulf (LOC #43613): 143 MMcf/d (leaving 0 MMcf/d)
Riverway (To Bridgeline) (LOC #42593): 90 MMcf/d (leaving 170 MMcf/d)
Avalon (LOC #38295): 90 MMcf/d (leaving 20 MMcf/d)
Shadyside/Sonat (Del) (LOC #10369): 202 MMcf/d (leaving 285 MMcf/d)
Shadyside/TGP (Del) (LOC #467240): 413 MMcf/d (leaving 30 MMcf/d)
St. Landry/FL Int (LOC #322625): Firm Primary only (previously shut in)
Weeks ISLA/LIG PL (LOC #233620): 298 MMcf/d (leaving 12 MMcf/d)
Opelousas (LOC #10111): 65 MMcf/d (leaving 15 MMcf/d)
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.
Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267
TSP
006958581
TSP Name
ANR Pipeline Company
Notice Type Desc
Plnd Outage
Posting Date/Time
08/27/2025 9:35 am
Notice Effective Date/Time
08/27/2025 9:35 am
Notice End Date/Time
09/02/2025 8:59 am
Notice ID
12543
Notice Status Desc
Supersede
Prior Notice
12531
Reqrd Rsp
5
Rsp Date/Time
Subject
UPDATED: CAPACITY REDUCTION - Southeast Area - Patterson Compressor Station (Updated: 8/27/25)
Notice Text
UPDATED: CAPACITY REDUCTION - Southeast Area - Patterson Compressor Station (Updated: 8/27/25)
ANR has revised the capacity impact for St. Landry/FL Int (LOC #322625) for the Patterson Compression Station maintenance in the Southeast Area. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. As a result, capacity will be reduced as follows:
8/27 - 9/1:
Patterson/Trunkline (LOC #40317): 94 MMcf/d (leaving 0 MMcf/d)
Patterson to Col Gulf (LOC #43613): 143 MMcf/d (leaving 0 MMcf/d)
Riverway (To Bridgeline) (LOC #42593): 90 MMcf/d (leaving 170 MMcf/d)
Avalon (LOC #38295): 90 MMcf/d (leaving 20 MMcf/d)
Shadyside/Sonat (Del) (LOC #10369): 202 MMcf/d (leaving 285 MMcf/d)
Shadyside/TGP (Del) (LOC #467240): 413 MMcf/d (leaving 30 MMcf/d)
St. Landry/FL Int (LOC #322625): Firm Primary only (previously shut in)
Weeks ISLA/LIG PL (LOC #233620): 298 MMcf/d (leaving 12 MMcf/d)
Opelousas (LOC #10111): 65 MMcf/d (leaving 15 MMcf/d)
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.
Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267
006958581
TSP Name
ANR Pipeline Company
Notice Type Desc
Plnd Outage
Posting Date/Time
08/27/2025 9:35 am
Notice Effective Date/Time
08/27/2025 9:35 am
Notice End Date/Time
09/02/2025 8:59 am
Notice ID
12543
Notice Status Desc
Supersede
Prior Notice
12531
Reqrd Rsp
5
Rsp Date/Time
Subject
UPDATED: CAPACITY REDUCTION - Southeast Area - Patterson Compressor Station (Updated: 8/27/25)
Notice Text
UPDATED: CAPACITY REDUCTION - Southeast Area - Patterson Compressor Station (Updated: 8/27/25)
ANR has revised the capacity impact for St. Landry/FL Int (LOC #322625) for the Patterson Compression Station maintenance in the Southeast Area. ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. As a result, capacity will be reduced as follows:
8/27 - 9/1:
Patterson/Trunkline (LOC #40317): 94 MMcf/d (leaving 0 MMcf/d)
Patterson to Col Gulf (LOC #43613): 143 MMcf/d (leaving 0 MMcf/d)
Riverway (To Bridgeline) (LOC #42593): 90 MMcf/d (leaving 170 MMcf/d)
Avalon (LOC #38295): 90 MMcf/d (leaving 20 MMcf/d)
Shadyside/Sonat (Del) (LOC #10369): 202 MMcf/d (leaving 285 MMcf/d)
Shadyside/TGP (Del) (LOC #467240): 413 MMcf/d (leaving 30 MMcf/d)
St. Landry/FL Int (LOC #322625): Firm Primary only (previously shut in)
Weeks ISLA/LIG PL (LOC #233620): 298 MMcf/d (leaving 12 MMcf/d)
Opelousas (LOC #10111): 65 MMcf/d (leaving 15 MMcf/d)
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract.