Planned Main Line Work between Stations 21-295 and 21-300

Carolina Gas Transmission 2mo ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Critical Desc
Critical notice

Notice ID
4535

Subject
Planned Main Line Work between Stations 21-295 and 21-300

Notice Type
Maintenance

Post D/T
7/25/2025 9:59:00 AM CCT

Notice Eff D/T
7/25/2025 9:59:00 AM CCT

Notice End D/T
8/12/2025 9:59:00 AM CCT

Notice Stat Desc
Initiate (a situation is being noticed)

Prior Notice


Reqrd Rsp Desc
No response required

TSP
09-499-2187

TSP Name
Carolina Gas Transmission, LLC

Notice Text

Carolina Gas Transmission (CGT) will be performing mainline work between Stations 21-295 and 21-300 in Chester County, SC. The work is scheduled for the week of July 28, 2025 and is expected to last five (5) days. This work will entail taking 6.3 miles of 8" mainline out of service while the work is being performed.

This outage is not expected to affect firm transportation but may impact IT and secondary FT.

If you have any questions, please call your Interstate Marketing Manager.



Attachments
No Attachments

Critical Desc
Critical notice

Notice ID
4535

Subject
Planned Main Line Work between Stations 21-295 and 21-300

Notice Type
Maintenance

Post D/T
7/25/2025 9:59:00 AM CCT

Notice Eff D/T
7/25/2025 9:59:00 AM CCT

Notice End D/T
8/12/2025 9:59:00 AM CCT

Notice Stat Desc
Initiate (a situation is being noticed)

Prior Notice


Reqrd Rsp Desc
No response required

TSP
09-499-2187

TSP Name
Carolina Gas Transmission, LLC

Notice Text

Carolina Gas Transmission (CGT) will be performing mainline work between Stations 21-295 and 21-300 in Chester County, SC. The work is scheduled for the week of July 28, 2025 and is expected to last five (5) days. This work will entail taking 6.3 miles of 8" mainline out of service while the work is being performed.

This outage is not expected to affect firm transportation but may impact IT and secondary FT.