Currently viewing the dev server.

Cove Point LNG Icon

Cove Point Restrictions Update

Cove Point LNG 1w ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Page 1

TSP Name / TSP: COVE POINT LNG LP (876833500)

Critical: Y

Posting Date/Time: 09/19/2025 09:30 AM

Notice Stat Desc: Supersede

Notice Eff Date/Time: 09/20/2025 10:00 AM

Notice ID: 1006598

Prior Notice: 1006484

Reqrd Rsp Desc: No response required

Response Date/Time:

Notice Type Desc: Capacity Constraint / Maintenance

Subject: Cove Point Restrictions Update

Notice Text:

Reminder: Due to the Planned Service Outage posted on 09/10/2025 (Notice ID #1006479), the following restrictions will be in effect during
the Pleasant Valley Station outage from 09/15/2025 through 10/10/2025. Customers are reminded that these restrictions are subject to
change based on actual operating conditions and available facilities. There are no changes from the previous Notice (ID 1006484).

For the time period of gas days 09/15/2025 – 09/19/2025: COMPLETED

Receipts from Columbia Loudoun (Loc 37001) and EGTS Loudoun (Loc 47001) will flow as scheduled.

Receipts from Transco Pleasant Valley (Loc 45001) will flow as scheduled up to an aggregated 750,000 dekatherms

based on priority of service.

Deliveries to Transco Pleasant Valley (Loc 45001) will flow as scheduled.

Primary Deliveries* to the Cove Point Delivery Locations will flow as scheduled.

Cove Point will deliver, in aggregate, up to 300,000 Dekatherms of Secondary and IT deliveries* across the Cove

Point Delivery Locations.

For gas days 09/20/2025 – 09/21/2025:

Receipts from Columbia Loudoun (Loc 37001) and EGTS Loudoun (Loc 47001) will flow as scheduled.

Receipts and Deliveries from/to Transco Pleasant Valley (Loc 45001) will not be scheduled

Primary Deliveries* to the Cove Point Delivery Locations will flow as scheduled.

Cove Point will deliver, in aggregate, up to 20,000 dekatherms of Secondary and IT deliveries* across the Cove

Point Delivery Locations.

For the time period of gas days 09/22/2025 – 10/10/2025:

Receipts from Columbia Loudoun (Loc 37001) and EGTS Loudoun (Loc 47001) will flow as scheduled.

Receipts from Transco Pleasant Valley (Loc 45001) will flow as scheduled up to an aggregated 300,000 dekatherms

based on priority of service.

Deliveries to Transco Pleasant Valley (Loc 45001) will flow as scheduled.

Primary Deliveries* to the Cove Point Delivery Locations will flow as scheduled.

Cove Point will deliver, in aggregate, up to 20,000 dekatherms of Secondary and IT deliveries* across the Cove

Point Delivery Locations.

Delivery Location

Name

77060  

WGL Willowsford

77010  

WGL Centreville

97000  

Ox into Possum Pt. Lateral

77020  

WGL White Plains

89000  

St. Charles M&R

77030  

Gardiner Road

88000  

Woodville M&R

87000  

Chalk Point Plant

77040  

WGL Prince Frederick

77050  

WGL Patuxent River

10002  

CVP Storage Point (ST)

Page 2

*Note that during this outage period, CPL may have limited ability to accept or manage non ratable hourly deliveries. 

Please continue to monitor these postings for further updates as estimates are subject to change. Please direct related questions to Ryan
Martin (ryan.martin@bhegts.com or 804.201.8804).  Power Generators should direct their requests to the CPL Power Desk.

TSP Name / TSP: COVE POINT LNG LP (876833500)
Critical: Y
Posting Date/Time: 09/19/2025 09:30 AM
Notice Stat Desc: Supersede
Notice Eff Date/Time: 09/20/2025 10:00 AM
Notice ID: 1006598
Prior Notice: 1006484
Reqrd Rsp Desc: No response required
Response Date/Time:
Notice Type Desc: Capacity Constraint / Maintenance
Subject: Cove Point Restrictions Update
Notice Text:
Reminder: Due to the Planned Service Outage posted on 09/10/2025 (Notice ID #1006479), the following restrictions will be in effect during
the Pleasant Valley Station outage from 09/15/2025 through 10/10/2025. Customers are reminded that these restrictions are subject to
change based on actual operating conditions and available facilities. There are no changes from the previous Notice (ID 1006484).
For the time period of gas days 09/15/2025 – 09/19/2025: COMPLETED
Receipts from Columbia Loudoun (Loc 37001) and EGTS Loudoun (Loc 47001) will flow as scheduled.
Receipts from Transco Pleasant Valley (Loc 45001) will flow as scheduled up to an aggregated 750,000 dekatherms
based on priority of service.
Deliveries to Transco Pleasant Valley (Loc 45001) will flow as scheduled.
Primary Deliveries* to the Cove Point Delivery Locations will flow as scheduled.
Cove Point will deliver, in aggregate, up to 300,000 Dekatherms of Secondary and IT deliveries* across the Cove
Point Delivery Locations.
For gas days 09/20/2025 – 09/21/2025:
Receipts from Columbia Loudoun (Loc 37001) and EGTS Loudoun (Loc 47001) will flow as scheduled.
Receipts and Deliveries from/to Transco Pleasant Valley (Loc 45001) will not be scheduled
Primary Deliveries* to the Cove Point Delivery Locations will flow as scheduled.
Cove Point will deliver, in aggregate, up to 20,000 dekatherms of Secondary and IT deliveries* across the Cove
Point Delivery Locations.
For the time period of gas days 09/22/2025 – 10/10/2025:
Receipts from Columbia Loudoun (Loc 37001) and EGTS Loudoun (Loc 47001) will flow as scheduled.
Receipts from Transco Pleasant Valley (Loc 45001) will flow as scheduled up to an aggregated 300,000 dekatherms
based on priority of service.
Deliveries to Transco Pleasant Valley (Loc 45001) will flow as scheduled.
Primary Deliveries* to the Cove Point Delivery Locations will flow as scheduled.
Cove Point will deliver, in aggregate, up to 20,000 dekatherms of Secondary and IT deliveries* across the Cove
Point Delivery Locations.
Delivery Location
Name
77060  
WGL Willowsford
77010  
WGL Centreville
97000  
Ox into Possum Pt. Lateral
77020  
WGL White Plains
89000  
St. Charles M&R
77030  
Gardiner Road
88000  
Woodville M&R
87000  
Chalk Point Plant
77040  
WGL Prince Frederick
77050  
WGL Patuxent River
10002  
CVP Storage Point (ST)
Page 1

*Note that during this outage period, CPL may have limited ability to accept or manage non ratable hourly deliveries. 
Please continue to monitor these postings for further updates as estimates are subject to change. Please direct related questions to Ryan
Martin (ryan.martin@bhegts.com or 804.201.8804).  Power Generators should direct their requests to the CPL Power Desk.
Page 2