COMP STA 168 - UNIT MAINTENANCE
Natural Gas Pipeline 1w ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP/TSP Name: 6931794-NATURAL GAS PIPELINE CO. | Critical: Y |
Notice Type Desc (1): MAINTENANCE | Notice Type Desc (2): MAINTENANCE |
Notice Eff Date/Time: 09/16/2025 4:19:47PM | Notice End Date/Time: 09/17/2025 9:00:00am |
Post Date/Time: 9/16/2025 4:19:47 PM | Notice ID: 46304 |
Reqrd Rsp: 1 | Rsp Date: 09/16/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: COMP STA 168 - UNIT MAINTENANCE |
COMPRESSOR STATION 168 – UNIT MAINTENANCE
Natural will be performing unit maintenance at Compressor Station 168 (CS 168) located in Bailey County, Texas (Segment 8 of Natural's Permian Zone). This maintenance work will require Natural to reduce the maximum operating capacity northbound into Segment 8 from Segment 9, thus limiting Natural's throughput capacity eastbound through CS 167 during this restriction.
The scheduling constraint will be in Segment 9 at CS 167; therefore, any gas received south of CS 167 for delivery north of CS 167 will be impacted for the duration of the restriction. The Pooling Point - Permian Zone (LOC 25077) is located south of the constraint. Firm transportation associated with storage withdrawals may be impacted.
As such, effective for gas day Thursday, September 18, 2025, Timely Cycle, and continuing through gas day Tuesday, September 30, 2025, Natural will schedule Primary Firm and Secondary in-path Firm transports to no less than 95% of contract MDQ through CS 167. AOR/ITS and Secondary out-of-path Firm transports will not be available for the duration of this restriction.
The stated scheduling percentage is based upon the current level of firm capacity contracted for during this restriction and is subject to change based upon operational conditions and Shipper utilization.
Continue to monitor Natural's interactive website for any updates during this restriction. Please contact your Account Director or Scheduling Representative if you have any questions.
TSP/TSP Name: 6931794-NATURAL GAS PIPELINE CO. | Critical: Y |
Notice Type Desc (1): MAINTENANCE | Notice Type Desc (2): MAINTENANCE |
Notice Eff Date/Time: 09/16/2025 4:19:47PM | Notice End Date/Time: 09/17/2025 9:00:00am |
Post Date/Time: 9/16/2025 4:19:47 PM | Notice ID: 46304 |
Reqrd Rsp: 1 | Rsp Date: 09/16/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: COMP STA 168 - UNIT MAINTENANCE |
COMPRESSOR STATION 168 – UNIT MAINTENANCE
Natural will be performing unit maintenance at Compressor Station 168 (CS 168) located in Bailey County, Texas (Segment 8 of Natural's Permian Zone). This maintenance work will require Natural to reduce the maximum operating capacity northbound into Segment 8 from Segment 9, thus limiting Natural's throughput capacity eastbound through CS 167 during this restriction.
The scheduling constraint will be in Segment 9 at CS 167; therefore, any gas received south of CS 167 for delivery north of CS 167 will be impacted for the duration of the restriction. The Pooling Point - Permian Zone (LOC 25077) is located south of the constraint. Firm transportation associated with storage withdrawals may be impacted.
As such, effective for gas day Thursday, September 18, 2025, Timely Cycle, and continuing through gas day Tuesday, September 30, 2025, Natural will schedule Primary Firm and Secondary in-path Firm transports to no less than 95% of contract MDQ through CS 167. AOR/ITS and Secondary out-of-path Firm transports will not be available for the duration of this restriction.
The stated scheduling percentage is based upon the current level of firm capacity contracted for during this restriction and is subject to change based upon operational conditions and Shipper utilization.
Continue to monitor Natural's interactive website for any updates during this restriction. Please contact your Account Director or Scheduling Representative if you have any questions.