NGTL Service (WGAT FT-D)
NGTL 4mo ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Capacity Constraint
Effective Start Date Time
05/22/2025 1:02 pm
Subject
NGTL Service (WGAT FT-D)
Notice Text
NGTL Service (WGAT FT-D)
USJR: N/A
WGAT: Due to upcoming planned maintenance on
the Burton Creek Compressor Station (19717034),
service allowable at Alberta-BC and Alberta Montana Border will transition from
100% IT-D and 100% FT-D to 0% IT-D and partial FT-D effective May 27, 2025 at 08:00 MST until further notice.
EGAT: N/A
Local Area/Location: N/A
New Information |
Updated Information |
Current and upcoming outages |
||||||
Outage ID |
Start |
End |
Facility/Outage Name |
Facility Type/Scope |
Outage Type |
Area of Impact |
19717034 |
May 27, 2025 |
June 1, 2025 |
Burton Creek |
Compressor Station Maintenance |
Planned |
WGAT |
Upstream
James River Receipt Area |
|||||||
Effective: |
May
16, 2025 at 08:00 MST |
IT Allowable: 20% |
IT-R |
IT-S (receipt) |
|
|
|
Expected End: |
Until
further notice |
FT Allowable: 100% |
FT-R |
FT-P |
|
|
|
Interconnects: |
Aitken Creek, Groundbirch
East, Gordondale |
||||||
Segments: |
|||||||
West
Gate Delivery Area |
||||||||||||
Effective: |
May
15, 2025 at 08:00 MST |
IT Allowable: 100% |
IT-D |
|
|
|
||||||
Expected End: |
May 27, 2025
at 08:00 MST |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
||||||
Interconnects: |
Alberta-B.C. Border and Alberta Montana
Border |
|||||||||||
Segments: |
||||||||||||
Effective: |
May 27, 2025 at 08:00 MST |
IT
Allowable: 0% |
IT-D |
|
|
|
|
|||||
Expected
End: |
Until further notice |
FT
Allowable: Partial |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
|||||
Interconnects: |
Alberta-B.C.
Border and Alberta Montana Border |
|||||||||||
Segments: |
Partial 21
(Alberta-B.C. Border and Alberta Montana Border) |
|||||||||||
East
Gate Delivery Area |
||||||
Effective: |
|
IT
Allowable: 100% |
IT-D |
IT-S (delivery) |
|
|
Expected
End: |
Until
further notice |
FT
Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
Interconnects: |
Aeco C, Carbon, Chancellor, Crossfield
East #2, Severn Creek, Empress, McNeil, Unity, Cold Lake, Warwick SE |
|||||
Segments: |
6, 10, 11, 13, 14,
15, 16, 17, 18, 19, 20, 23, 24, partial 21 and partial 28 (Greater EGAT) |
Local Area/Location |
N/A |
If there is an overlap
between Local Area/Location and Upstream James River Receipt Area, West Gate
Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT
Allowable will be in effect. The details in this bulletin supersede any
previously published information and will be reflected and maintained in the
next release of the Daily Operating Plan.
Capacity Constraint
Effective Start Date Time
05/22/2025 1:02 pm
Subject
NGTL Service (WGAT FT-D)
Notice Text
NGTL Service (WGAT FT-D)
USJR: N/A
WGAT: Due to upcoming planned maintenance on
the Burton Creek Compressor Station (19717034),
service allowable at Alberta-BC and Alberta Montana Border will transition from
100% IT-D and 100% FT-D to 0% IT-D and partial FT-D effective May 27, 2025 at 08:00 MST until further notice.
EGAT: N/A
Local Area/Location: N/A
New Information |
Updated Information |
Current and upcoming outages |
||||||
Outage ID |
Start |
End |
Facility/Outage Name |
Facility Type/Scope |
Outage Type |
Area of Impact |
19717034 |
May 27, 2025 |
June 1, 2025 |
Burton Creek |
Compressor Station Maintenance |
Planned |
WGAT |
Upstream
James River Receipt Area |
|||||||
Effective: |
May
16, 2025 at 08:00 MST |
IT Allowable: 20% |
IT-R |
IT-S (receipt) |
|
|
|
Expected End: |
Until
further notice |
FT Allowable: 100% |
FT-R |
FT-P |
|
|
|
Interconnects: |
Aitken Creek, Groundbirch
East, Gordondale |
||||||
Segments: |
|||||||
West
Gate Delivery Area |
||||||||||||
Effective: |
May
15, 2025 at 08:00 MST |
IT Allowable: 100% |
IT-D |
|
|
|
||||||
Expected End: |
May 27, 2025
at 08:00 MST |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
||||||
Interconnects: |
Alberta-B.C. Border and Alberta Montana
Border |
|||||||||||
Segments: |
||||||||||||
Effective: |
May 27, 2025 at 08:00 MST |
IT
Allowable: 0% |
IT-D |
|
|
|
|
|||||
Expected
End: |
Until further notice |
FT
Allowable: Partial |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
|||||
Interconnects: |
Alberta-B.C.
Border and Alberta Montana Border |
|||||||||||
Segments: |
Partial 21
(Alberta-B.C. Border and Alberta Montana Border) |
|||||||||||
East
Gate Delivery Area |
||||||
Effective: |
|
IT
Allowable: 100% |
IT-D |
IT-S (delivery) |
|
|
Expected
End: |
Until
further notice |
FT
Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
Interconnects: |
Aeco C, Carbon, Chancellor, Crossfield
East #2, Severn Creek, Empress, McNeil, Unity, Cold Lake, Warwick SE |
|||||
Segments: |
6, 10, 11, 13, 14,
15, 16, 17, 18, 19, 20, 23, 24, partial 21 and partial 28 (Greater EGAT) |
Local Area/Location |
N/A |
If there is an overlap
between Local Area/Location and Upstream James River Receipt Area, West Gate
Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT
Allowable will be in effect. The details in this bulletin supersede any
previously published information and will be reflected and maintained in the
next release of the Daily Operating Plan.