NGTL Service (USJR IT-R, USJR IT-D EGAT IT-D)
NGTL 3mo ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Capacity Constraint
Effective Start Date Time
06/26/2025 12:29 pm
Subject
NGTL Service (USJR IT-R, USJR IT-D EGAT IT-D)
Notice Text
NGTL Service (USJR IT-R, USJR
IT-D, EGAT IT-D)
USJR: Planned
maintenance on the Meikle River D5 Compressor Station (19717024) is ongoing and
on track for completion June 26, 2025. Effective June 27, 2025
at 08:00 MST:
· Segments
2, 3, 4, and partial 7 (Upstream of Latornell) will
transition from 0% IT-R and 100% FT-R to 100% IT-R and 100% FT-R
· Segments
8, 9, and partial 7 (Downstream of Latornell) will
transition from 0% IT-D and 100% FT-D to 100% IT-D and 100% FT-D
WGAT: N/A
EGAT: Planned
maintenance on the Meikle River D5 Compressor Station (19717024) and Didsbury
Compressor Station (19724808) are ongoing and on track for completion June 26,
2025. Effective June 27, 2025 at 08:00 MST, service
allowable for Segments 6, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24,
partial 21, and partial 28 (Greater EGAT) will transition from 0% IT-D and 100%
FT-D to 100% IT-D and 100% FT-D until further notice.
New Information |
Updated Information |
Current and upcoming outages |
||||||
Outage ID |
Start |
End |
Facility/Outage Name |
Facility Type/Scope |
Outage Type |
Area of Impact |
19724808 |
June 16, 2025 |
June 26, 2025 |
Didsbury |
Compressor Station Maintenance |
Planned |
EGAT |
19717024 |
June
23, 2025 |
June
26, 2025 |
Meikle River D5 |
Compressor
Station Maintenance |
Planned |
USJR |
Upstream James River Area |
|||||
Effective: |
June
23, 2025 at 08:00 MST |
IT Allowable: 0% |
IT-R |
IT-S
(receipt) |
|
Expected End: |
June 27, 2025
at 08:00 MST |
FT Allowable: 100% |
FT-R |
FT-P |
|
Interconnects: |
Aitken Creek, Gordondale,
Groundbirch East |
||||
Segments: |
|||||
Effective: |
June
23, 2025 at 08:00 MST |
IT Allowable: 0% |
IT-D |
IT-S (delivery) |
|
Expected End: |
June 27, 2025 at 08:00 MST |
FT Allowable: 100% |
FT-D |
FT-P |
|
Interconnects: |
Big Eddy, January Creek |
||||
Segments: |
|||||
Effective: |
June 27, 2025
at 08:00 MST |
IT Allowable:
100% |
IT-R |
IT-S (receipt) |
|
Expected End: |
Until Further Notice |
FT Allowable: 100% |
FT-R |
FT-P |
|
Interconnects: |
Aitken
Creek, Big Eddy, Gordondale, Groundbirch
East, January Creek |
||||
Segments: |
West Gate Area |
||||||
Effective: |
June 02, 2025 at 08:00 MST |
IT Allowable:
100% |
IT-D |
|||
Expected End: |
Until
further notice |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
Interconnects: |
Alberta-B.C. Border and Alberta Montana
Border |
|||||
Segments: |
East Gate Area |
||||||
Effective: |
June 23, 2025 at 08:00 MST |
IT Allowable: 0% |
IT-D |
IT-S (delivery) |
||
Expected End: |
June 27, 2025
at 08:00 MST |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
Interconnects: |
Aeco C, Carbon,
Chancellor, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Warwick
SE |
|||||
Segments: |
6, 10, 11, 13, 14,
15, 16, 17, 18, 19, 20, 23, 24, partial 21, and partial 28 (Greater EGAT) |
|||||
Effective: |
June 27, 2025
at 08:00 MST |
IT
Allowable: 100% |
IT-D |
IT-S
(delivery) |
||
Expected
End: |
Until further notice |
FT
Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
Interconnects: |
Aeco C, Carbon, Chancellor, Cold Lake, Crossfield East
#2, Severn Creek, Empress, McNeil, Unity, Warwick SE |
|||||
Segments: |
6, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24,
partial 21, and partial 28 (Greater EGAT) |
If there is an overlap
between Local Area/Location and Upstream James River Receipt Area, West Gate
Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT
Allowable will be in effect. The details in this bulletin supersede any
previously published information and will be reflected and maintained in the
next release of the Daily Operating Plan.
Capacity Constraint
Effective Start Date Time
06/26/2025 12:29 pm
Subject
NGTL Service (USJR IT-R, USJR IT-D EGAT IT-D)
Notice Text
NGTL Service (USJR IT-R, USJR
IT-D, EGAT IT-D)
USJR: Planned
maintenance on the Meikle River D5 Compressor Station (19717024) is ongoing and
on track for completion June 26, 2025. Effective June 27, 2025
at 08:00 MST:
· Segments
2, 3, 4, and partial 7 (Upstream of Latornell) will
transition from 0% IT-R and 100% FT-R to 100% IT-R and 100% FT-R
· Segments
8, 9, and partial 7 (Downstream of Latornell) will
transition from 0% IT-D and 100% FT-D to 100% IT-D and 100% FT-D
WGAT: N/A
EGAT: Planned
maintenance on the Meikle River D5 Compressor Station (19717024) and Didsbury
Compressor Station (19724808) are ongoing and on track for completion June 26,
2025. Effective June 27, 2025 at 08:00 MST, service
allowable for Segments 6, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24,
partial 21, and partial 28 (Greater EGAT) will transition from 0% IT-D and 100%
FT-D to 100% IT-D and 100% FT-D until further notice.
New Information |
Updated Information |
Current and upcoming outages |
||||||
Outage ID |
Start |
End |
Facility/Outage Name |
Facility Type/Scope |
Outage Type |
Area of Impact |
19724808 |
June 16, 2025 |
June 26, 2025 |
Didsbury |
Compressor Station Maintenance |
Planned |
EGAT |
19717024 |
June
23, 2025 |
June
26, 2025 |
Meikle River D5 |
Compressor
Station Maintenance |
Planned |
USJR |
Upstream James River Area |
|||||
Effective: |
June
23, 2025 at 08:00 MST |
IT Allowable: 0% |
IT-R |
IT-S
(receipt) |
|
Expected End: |
June 27, 2025
at 08:00 MST |
FT Allowable: 100% |
FT-R |
FT-P |
|
Interconnects: |
Aitken Creek, Gordondale,
Groundbirch East |
||||
Segments: |
|||||
Effective: |
June
23, 2025 at 08:00 MST |
IT Allowable: 0% |
IT-D |
IT-S (delivery) |
|
Expected End: |
June 27, 2025 at 08:00 MST |
FT Allowable: 100% |
FT-D |
FT-P |
|
Interconnects: |
Big Eddy, January Creek |
||||
Segments: |
|||||
Effective: |
June 27, 2025
at 08:00 MST |
IT Allowable:
100% |
IT-R |
IT-S (receipt) |
|
Expected End: |
Until Further Notice |
FT Allowable: 100% |
FT-R |
FT-P |
|
Interconnects: |
Aitken
Creek, Big Eddy, Gordondale, Groundbirch
East, January Creek |
||||
Segments: |
West Gate Area |
||||||
Effective: |
June 02, 2025 at 08:00 MST |
IT Allowable:
100% |
IT-D |
|||
Expected End: |
Until
further notice |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
Interconnects: |
Alberta-B.C. Border and Alberta Montana
Border |
|||||
Segments: |
East Gate Area |
||||||
Effective: |
June 23, 2025 at 08:00 MST |
IT Allowable: 0% |
IT-D |
IT-S (delivery) |
||
Expected End: |
June 27, 2025
at 08:00 MST |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
Interconnects: |
Aeco C, Carbon,
Chancellor, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Warwick
SE |
|||||
Segments: |
6, 10, 11, 13, 14,
15, 16, 17, 18, 19, 20, 23, 24, partial 21, and partial 28 (Greater EGAT) |
|||||
Effective: |
June 27, 2025
at 08:00 MST |
IT
Allowable: 100% |
IT-D |
IT-S
(delivery) |
||
Expected
End: |
Until further notice |
FT
Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
Interconnects: |
Aeco C, Carbon, Chancellor, Cold Lake, Crossfield East
#2, Severn Creek, Empress, McNeil, Unity, Warwick SE |
|||||
Segments: |
6, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24,
partial 21, and partial 28 (Greater EGAT) |
If there is an overlap
between Local Area/Location and Upstream James River Receipt Area, West Gate
Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT
Allowable will be in effect. The details in this bulletin supersede any
previously published information and will be reflected and maintained in the
next release of the Daily Operating Plan.