RESTRICTIONS FOR 12-08-2025 EC
Tennessee Gas Pipeline 1d ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
| TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
| Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
| Notice Eff Date/Time: 12/07/2025 7:18:04PM | Notice End Date/Time: 12/08/2025 9:00:00am |
| Post Date/Time: 12/7/2025 7:18:04 PM | Notice ID: 397582 |
| Reqrd Rsp: 1 | Rsp Date: 12/07/2025 |
| Notice Stat Desc: INITIATE | Prior Notice: |
| Subject: RESTRICTIONS FOR 12-08-2025 EC |
Effective Evening Cycle (9:00) for the gas day of Monday, December 08, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES 4, 5 AND 6 FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
OFO DAILY CRTICAL DAY 1 FOR THE 500 LINE (SEGMENTS 527, 529, 539, 530, 534, 542, 548, 860) FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
EXCESSIVE HOURLY TAKES WARNING FOR ALL AREAS EAST OF STA 249 ON THE 200 LINE
METER RESTRICTIONS
· GULF SOUTH/TGP Kiln Miss Exchange Hanc Receipt Meter (Pin 420383) - through 100% of SOP increases receipts due to displacement gas unavailable for backhaul; 4,992 Dths
SEGMENT RESTRICTIONS
· STA 47 (Segment 143 FH) - through approx 52% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 130,555 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to operational concerns; 1,948 Dths
· STA 834 (Segment 834 BH) - through 100% of SA increases due to scheduled maintenance and nominations in excess of operational capacity; 5,100 Dths
· STA 523 West (Segment 516 FH) - through approx 86% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 47,428 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 343,132 Dths
· MLV 314 East (Segment 314 BH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 219,405 Dths
· STA 315 (Segment 315 BH) - through approx 61% of SOP increases due to nominations in excess of oper ational capacity; 143,082 Dths
· STA 317 (Segment 317 BH) - through approx 69% of SOP increases due to nominations in excess of operational capacity; 64,000 Dths
· STA 321 (Segment 321 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 802,999 Dths
· STA 325 (Segment 324 FH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 229,112 Dths
· MLV 330 (Segment 324 FH) - through approx 58% of SOP increases due to nominations in excess of operational capacity; 8,791 Dths
· STA 224 (Segment 224 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 135,200 Dths
· Z5 HC North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 292,635 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 441,654 Dths
· STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 365,006 Dths
· STA 254 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 257,537 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 105,232 Dths
· STA 268 North (Segment 268 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 735 Dths
LINEPACK RESTRICTIONS
NONE
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
| TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
| Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
| Notice Eff Date/Time: 12/07/2025 7:18:04PM | Notice End Date/Time: 12/08/2025 9:00:00am |
| Post Date/Time: 12/7/2025 7:18:04 PM | Notice ID: 397582 |
| Reqrd Rsp: 1 | Rsp Date: 12/07/2025 |
| Notice Stat Desc: INITIATE | Prior Notice: |
| Subject: RESTRICTIONS FOR 12-08-2025 EC |
Effective Evening Cycle (9:00) for the gas day of Monday, December 08, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES 4, 5 AND 6 FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
OFO DAILY CRTICAL DAY 1 FOR THE 500 LINE (SEGMENTS 527, 529, 539, 530, 534, 542, 548, 860) FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
EXCESSIVE HOURLY TAKES WARNING FOR ALL AREAS EAST OF STA 249 ON THE 200 LINE
METER RESTRICTIONS
· GULF SOUTH/TGP Kiln Miss Exchange Hanc Receipt Meter (Pin 420383) - through 100% of SOP increases receipts due to displacement gas unavailable for backhaul; 4,992 Dths
SEGMENT RESTRICTIONS
· STA 47 (Segment 143 FH) - through approx 52% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 130,555 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to operational concerns; 1,948 Dths
· STA 834 (Segment 834 BH) - through 100% of SA increases due to scheduled maintenance and nominations in excess of operational capacity; 5,100 Dths
· STA 523 West (Segment 516 FH) - through approx 86% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 47,428 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 343,132 Dths
· MLV 314 East (Segment 314 BH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 219,405 Dths
· STA 315 (Segment 315 BH) - through approx 61% of SOP increases due to nominations in excess of oper ational capacity; 143,082 Dths
· STA 317 (Segment 317 BH) - through approx 69% of SOP increases due to nominations in excess of operational capacity; 64,000 Dths
· STA 321 (Segment 321 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 802,999 Dths
· STA 325 (Segment 324 FH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 229,112 Dths
· MLV 330 (Segment 324 FH) - through approx 58% of SOP increases due to nominations in excess of operational capacity; 8,791 Dths
· STA 224 (Segment 224 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 135,200 Dths
· Z5 HC North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 292,635 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 441,654 Dths
· STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 365,006 Dths
· STA 254 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 257,537 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 105,232 Dths
· STA 268 North (Segment 268 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 735 Dths
LINEPACK RESTRICTIONS
NONE
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.