TransCanada Canadian Mainline Icon

Prairies Pipeline System Maintenance July 6 to July 11

TransCanada Canadian Mainline 21h ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Notice Type
Capacity Constraint

Effective Start Date Time
06/23/2025 7:45 pm

Subject
Prairies Pipeline System Maintenance July 6 to July 11

Notice Text

In-line inspections will be conducted on Line 5 of the Prairies pipeline system from gas days July 6th to July 11th inclusive.

 

Depending on demand levels, discretionary services may be limited through the MDA to downstream locations. Firm services are not anticipated to be impacted.

 

Prairies capacity is expected to be approximately 4750 TJ/d for the maintenance period and will be reflected in the June 26, 2025 Maintenance Capacity postings.

 

Note that system capacities are variable due to many factors including forecast delivery distribution, ambient temperatures, gas stream energy content, facility availability, and interconnect assistance as applicable.  Actual capacities on the day may vary due to changes to the maintenance schedule, unplanned events, and differences between forecast and actual conditions.

 

 

QUESTIONS

If you have any questions or require further information, please contact your Marketing Representative



Notice Type
Capacity Constraint

Effective Start Date Time
06/23/2025 7:45 pm

Subject
Prairies Pipeline System Maintenance July 6 to July 11

Notice Text

In-line inspections will be conducted on Line 5 of the Prairies pipeline system from gas days July 6th to July 11th inclusive.

 

Depending on demand levels, discretionary services may be limited through the MDA to downstream locations. Firm services are not anticipated to be impacted.

 

Prairies capacity is expected to be approximately 4750 TJ/d for the maintenance period and will be reflected in the June 26, 2025 Maintenance Capacity postings.

 

Note that system capacities are variable due to many factors including forecast delivery distribution, ambient temperatures, gas stream energy content, facility availability, and interconnect assistance as applicable.  Actual capacities on the day may vary due to changes to the maintenance schedule, unplanned events, and differences between forecast and actual conditions.

 

 

QUESTIONS

If you have any questions or require further information, please contact your Marketing Representative