Reminder: Station 2 Maintenance Work - Sept to Nov
TransCanada Canadian Mainline 4d ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Other
Effective Start Date Time
09/23/2025 9:24 pm
Subject
Reminder: Station 2 Maintenance Work - Sept to Nov
Notice Text
TC Energy provides an update and reminder that required upgrades and reliability work at Station 2 as previously announced is ongoing. Loss of critical unit (LCU) protection at Station 2 on the Prairies Pipeline System will be limited until November.
During this period, Prairies system capacity is expected to remain similar to current levels in capacity postings. However, there will be a higher risk to firm and discretionary services should an additional unplanned compressor unit outage occur at Station 2, or at downstream compressor station facilities in the SSDA.
The dates of maintenance where LCU protection will be limited are:
September 2-30
October 1-2 & 20-21
November 3-21
TC Energy will continue to regularly communicate updates on progress of work and system capacity via Bulletins.
QUESTIONS
If you have any questions or require further information, please contact your Marketing Representative
Other
Effective Start Date Time
09/23/2025 9:24 pm
Subject
Reminder: Station 2 Maintenance Work - Sept to Nov
Notice Text
TC Energy provides an update and reminder that required upgrades and reliability work at Station 2 as previously announced is ongoing. Loss of critical unit (LCU) protection at Station 2 on the Prairies Pipeline System will be limited until November.
During this period, Prairies system capacity is expected to remain similar to current levels in capacity postings. However, there will be a higher risk to firm and discretionary services should an additional unplanned compressor unit outage occur at Station 2, or at downstream compressor station facilities in the SSDA.
The dates of maintenance where LCU protection will be limited are:
September 2-30
October 1-2 & 20-21
November 3-21
TC Energy will continue to regularly communicate updates on progress of work and system capacity via Bulletins.
QUESTIONS
If you have any questions or require further information, please contact your Marketing Representative