Currently viewing the dev server.

Westcoast Energy Icon

Sunset Creek Interconnect Capacity for September 24 - 30, 2025

Westcoast Energy 4d ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

 

Westcoast Energy Limited Partnership

Critical Notice

Curtailment - Pipeline

 

Notice:

 #59789

Revision: 

 #0

 

Subject:

Sunset Creek Interconnect Capacity for September 24 - 30, 2025

 

Summary:

Sunset Creek Interconnect Capacity for September 24 - 30, 2025

Further to Notice #59703, Westcoast will be allowing the following flow at Sunset Creek Interconnect:

Sunset Creek Interconnect Capacity

September 24 - 30, 2025:          1,389,615 GJ

Changes in operating conditions may result in the capacity being recalled on any gas cycle.

If you have any questions, please contact the CSR hotline at (403) 699-1800.

 

Posting Date:23-Sep-2025 07:46 CCT
Effective Date:23-Sep-2025
End Date:30-Sep-2025
Response Date:N/A
Location:N/A
Contacts:N/A
 

Westcoast Energy Limited Partnership

Critical Notice

Curtailment - Pipeline

 

Notice:

 #59789

Revision: 

 #0

 

Subject:

Sunset Creek Interconnect Capacity for September 24 - 30, 2025

 

Summary:

Sunset Creek Interconnect Capacity for September 24 - 30, 2025

Further to Notice #59703, Westcoast will be allowing the following flow at Sunset Creek Interconnect:

Sunset Creek Interconnect Capacity

September 24 - 30, 2025:          1,389,615 GJ

Changes in operating conditions may result in the capacity being recalled on any gas cycle.

If you have any questions, please contact the CSR hotline at (403) 699-1800.

 

Posting Date:23-Sep-2025 07:46 CCT
Effective Date:23-Sep-2025
End Date:30-Sep-2025
Response Date:N/A
Location:N/A