Planned Service Outage – North Zone A

Project #21.009 – North Zone A. As a result of this work, on gas day 12/10/2021,
secondary receipt at Gilbert will be limited to 15,000 dth/day and no secondary
receipts at Quakertown will be scheduled. At this time, we anticipate a return to
normal system operations by the start of gas day 12/11/2021.

Adelphia will notify shippers when the restrictions are lifted.

Please contact your Transportation Services Representative should you have any
questions 732-245-3169.


December 9, 2021


Planned Service Outage – North Zone A

Project #21.009 – North Zone A. As a result of this work, on gas day 12/10/2021,
secondary receipt at Gilbert will be limited to 15,000 dth/day and no secondary
receipts at Quakertown will be scheduled. At this time, we anticipate a return to
normal system operations by the start of gas day 12/11/2021.

Adelphia will notify shippers when the restrictions are lifted.

Please contact your Transportation Services Representative should you have any