VECTOR – GUARDIAN PIPELINE INTERCONNECT OUTAGE DATE CHANGE

OCTOBER 30-NOVEMBER 2, 2023

Pursuant to the attached planned service outage notices posted 10/19/23 by Vector Pipeline, VECTOR

interconnect with Guardian will be unavailable for Gas Days 10/30/2023 – 11/2/2023. On these Gas

Days, Bluewater will not be able to receive or deliver gas at Vector/Guardian Joliet.

Please contact your account manager with any questions or concerns.
See attachment on next two pages.

VECTOR POSTING

*** IMPORTANT OUTAGE UPDATE ***

VECTOR

– GUARDIAN PIPELINE INTERCONNECT OUTAGE

OCTOBER 30-NOVEMBER 2, 2023


October 19, 2023

To Vector Shippers:

Major facility upgrades are planned at the Alliance and Northern Border Interconnections in Will
County, Illinois (refer to separate Critical Posting). The Guardian Interconnection will need to be
isolated for several days in order to complete the work at those sites. The originally planned
work at Guardian on October 23-25 is now tentatively scheduled for October 30-November
2, 2023.
No commercial activity to be scheduled at the Guardian Interconnection. The
Locations impacted include the meters, PAL and TTS points (GU151, GU-PAL and GU-TTS).

Please refer to a separate posting regarding Vector’s interconnection with Alliance and Northern
Border Interconnections.

These outages wil impact Vector’s firm service contracts and Demand Charge Credit
mechanisms und

er Vector’s FERC (GT&C Section 41) Gas Tariff wil apply.


Any inquiries or concerns should be directed to the following Marketing contacts:

Matt Malinowski

– Director, Market Development

(734) 276-6189

Dennis Scheibe

– Manager, Transportation Services

(734) 210-8481


Vector Pipeline

38705 Seven Mile Road
Suite 490
Livonia, MI 48152
USA

VECTOR POSTING

*** IMPORTANT OUTAGE UPDATE ***

VECTOR

– ALLIANCE AND NORTHERN BORDER INTERCONNECTS OUTAGES

SEPTEMBER 19

– NOVEMBER 16, 2023


October 19, 2023

To Vector Shippers:

Major facility upgrades are planned at the Alliance and Northern Border Interconnections in Will
County, Illinois. The meters and flow control valves at these interconnections are being
replaced with equipment better suited for the smaller volume of gas that now flows at these
sites. This work will impact all transportation services at the interconnections for several weeks.
Due to construction delays, the outage will tentatively extend through November 16, 2023
and no commercial services will be scheduled during this time.
The Locations impacted
include the meters, PAL and TTS points (AL101, ALL-PAL, ALL-TTS, NB101, NB-PAL and NB-
TTS).

Please refer to a separate posting regarding Vector’s interconnection with Guardian Pipeline.

These outages wil impact Vector’s firm service contracts and Demand Charge Credit
mechanisms under Vector’s FERC (GT&C Section 41) Gas Tariff wil apply.

Any inquiries or concerns should be directed to the following Marketing contacts:

Matt Malinowski

– Director, Market Development

(734) 276-6189

Dennis Scheibe

– Manager, Transportation Services

(734) 210-8481


Vector Pipeline


38705 Seven Mile Road
Suite 490
Livonia, MI 48152
USA

Document Outline


VECTOR – GUARDIAN PIPELINE INTERCONNECT OUTAGE DATE CHANGE
OCTOBER 30-NOVEMBER 2, 2023
Pursuant to the attached planned service outage notices posted 10/19/23 by Vector Pipeline, VECTOR
interconnect with Guardian will be unavailable for Gas Days 10/30/2023 – 11/2/2023. On these Gas
Days, Bluewater will not be able to receive or deliver gas at Vector/Guardian Joliet.
Please contact your account manager with any questions or concerns.
See attachment on next two pages.

38705 Seven Mile Road
Suite 490
Livonia, MI 48152
USA

VECTOR POSTING

*** IMPORTANT OUTAGE UPDATE ***
VECTOR – GUARDIAN PIPELINE INTERCONNECT OUTAGE
OCTOBER 30-NOVEMBER 2, 2023

October 19, 2023
To Vector Shippers:

Major facility upgrades are planned at the Alliance and Northern Border Interconnections in Will
County, Illinois (refer to separate Critical Posting). The Guardian Interconnection will need to be
isolated for several days in order to complete the work at those sites. The originally planned
work at Guardian on October 23-25 is now tentatively scheduled for October 30-November
2, 2023.
No commercial activity to be scheduled at the Guardian Interconnection. The
Locations impacted include the meters, PAL and TTS points (GU151, GU-PAL and GU-TTS).

Please refer to a separate posting regarding Vector’s interconnection with Alliance and Northern
Border Interconnections.

These outages wil impact Vector’s firm service contracts and Demand Charge Credit
mechanisms under Vector’s FERC (GT&C Section 41) Gas Tariff wil apply.

Any inquiries or concerns should be directed to the following Marketing contacts:

Matt Malinowski – Director, Market Development
(734) 276-6189

Dennis Scheibe – Manager, Transportation Services
(734) 210-8481












Vector Pipeline

38705 Seven Mile Road
Suite 490
Livonia, MI 48152
USA

VECTOR POSTING

*** IMPORTANT OUTAGE UPDATE ***
VECTOR – ALLIANCE AND NORTHERN BORDER INTERCONNECTS OUTAGES
SEPTEMBER 19 – NOVEMBER 16, 2023

October 19, 2023
To Vector Shippers:

Major facility upgrades are planned at the Alliance and Northern Border Interconnections in Will
County, Illinois. The meters and flow control valves at these interconnections are being
replaced with equipment better suited for the smaller volume of gas that now flows at these
sites. This work will impact all transportation services at the interconnections for several weeks.
Due to construction delays, the outage will tentatively extend through November 16, 2023
and no commercial services will be scheduled during this time.
The Locations impacted
include the meters, PAL and TTS points (AL101, ALL-PAL, ALL-TTS, NB101, NB-PAL and NB-
TTS).

Please refer to a separate posting regarding Vector’s interconnection with Guardian Pipeline.

These outages wil impact Vector’s firm service contracts and Demand Charge Credit
mechanisms under Vector’s FERC (GT&C Section 41) Gas Tariff wil apply.

Any inquiries or concerns should be directed to the following Marketing contacts:

Matt Malinowski – Director, Market Development
(734) 276-6189

Dennis Scheibe – Manager, Transportation Services
(734) 210-8481