Adding proxy2: 8489 Adding proxy2: 8671 Adding proxy2: 8567 Carolina Gas Transmission Notice 4536 - API PipeRiv

Currently viewing the dev server.

Carolina Gas Transmission Notice 4536

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Critical Desc
Critical notice

Notice ID
4536

Subject
August 2025 Pipeline Work

Notice Type
Maintenance

Post D/T
7/30/2025 12:30:00 PM CCT

Notice Eff D/T
7/30/2025 12:30:00 PM CCT

Notice End D/T
9/5/2025 12:30:00 PM CCT

Notice Stat Desc
Initiate (a situation is being noticed)

Prior Notice


Reqrd Rsp Desc
No response required

TSP
09-499-2187

TSP Name
Carolina Gas Transmission, LLC

Notice Text

Carolina Gas Transmission (CGT) will be doing the following pipeline work from August 1st, 2025, through August 31st, 2025.

Line Outages of the following pipe segments will involve controlled releases of natural gas. These outages are not expected to affect firm transportation but may impact IT and secondary FT.

  • Approximately 13 miles of 6" line between Stations 13-010 and 13-070 in Darlington County, SC was taken out of service January 11th 2023 and its return to service date is unknown at this time.

  • Approximately 1.7 miles of 6" line between Stations 13-140 and 13-150 in Florence County, SC will be taken out of service from August 18th, 2025, until August 22nd, 2025.

If you have any questions, please call your Interstate Marketing Manager.



Attachments
No Attachments

Critical Desc
Critical notice

Notice ID
4536

Subject
August 2025 Pipeline Work

Notice Type
Maintenance

Post D/T
7/30/2025 12:30:00 PM CCT

Notice Eff D/T
7/30/2025 12:30:00 PM CCT

Notice End D/T
9/5/2025 12:30:00 PM CCT

Notice Stat Desc
Initiate (a situation is being noticed)

Prior Notice


Reqrd Rsp Desc
No response required

TSP
09-499-2187

TSP Name
Carolina Gas Transmission, LLC

Notice Text

Carolina Gas Transmission (CGT) will be doing the following pipeline work from August 1st, 2025, through August 31st, 2025.

Line Outages of the following pipe segments will involve controlled releases of natural gas. These outages are not expected to affect firm transportation but may impact IT and secondary FT.

  • Approximately 13 miles of 6" line between Stations 13-010 and 13-070 in Darlington County, SC was taken out of service January 11th 2023 and its return to service date is unknown at this time.

  • Approximately 1.7 miles of 6" line between Stations 13-140 and 13-150 in Florence County, SC will be taken out of service from August 18th, 2025, until August 22nd, 2025.

If you have any questions, please call your Interstate Marketing Manager.



Attachments
No Attachments