Columbia Gas Transmission Notice 25943613
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
|
TSP Name
Columbia Gas Transmission, LLC
TSP
054748041
Date
Time
Notice ID
25943613
Notice Type Description: Maintenance
Notice Stat Desc: Initiate
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
08/05/25
08/05/25
09/05/25
2:50:27 PM
12:00:00 AM
12:00:00 AM
Subject: Construction and Maintenance Schedule Posting
Author: Dillon Schoolcraft
Notice Text
As a courtesy, Columbia Gas Transmission, LLC (TCO) hereby notifies customers the Construction and Maintenance Schedule posted under "Construction and Maintenance" on the Informational Postings website has been updated. TCO reminds customers to please check the Maintenance Schedule on a regular basis. The current schedule has been updated to reflect maintenance activity on the following: * Revised dates for both Line H outages - August 18 - September 1, 2025 & September 2 - October 1, 2025 (Previously scheduled for August 11 - August 25, 2025 & August 26 - September 26, 2025) * Revised start date for WB Loop Maintenance - September 8-30, 2025 (Previously schedule to start on September 10, 2025) * Revised dates for L-2542 Pipeline Maintenance - September 16-24, 2025* L-2542 Pipeline Maintenance - October 24-27, 2025
Additionally, the following file(s) can be located on Informational Postings under Construction and Maintenance
TCO Construction and Maintenance Schedule 08-05-2025.pdf
Columbia Gas Transmission, LLC
TSP
054748041
Date
Time
Notice ID
25943613
Notice Type Description: Maintenance
Notice Stat Desc: Initiate
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
08/05/25
08/05/25
09/05/25
2:50:27 PM
12:00:00 AM
12:00:00 AM
Subject: Construction and Maintenance Schedule Posting
Author: Dillon Schoolcraft
Notice Text
As a courtesy, Columbia Gas Transmission, LLC (TCO) hereby notifies customers the Construction and Maintenance Schedule posted under "Construction and Maintenance" on the Informational Postings website has been updated. TCO reminds customers to please check the Maintenance Schedule on a regular basis. The current schedule has been updated to reflect maintenance activity on the following: * Revised dates for both Line H outages - August 18 - September 1, 2025 & September 2 - October 1, 2025 (Previously scheduled for August 11 - August 25, 2025 & August 26 - September 26, 2025) * Revised start date for WB Loop Maintenance - September 8-30, 2025 (Previously schedule to start on September 10, 2025) * Revised dates for L-2542 Pipeline Maintenance - September 16-24, 2025* L-2542 Pipeline Maintenance - October 24-27, 2025
Additionally, the following file(s) can be located on Informational Postings under Construction and Maintenance
TCO Construction and Maintenance Schedule 08-05-2025.pdf