Cove Point LNG Notice 1006484
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Page 1
TSP Name / TSP: COVE POINT LNG LP (876833500)
Critical: Y
Posting Date/Time: 09/10/2025 01:13 PM
Notice Stat Desc: Supersede
Notice Eff Date/Time: 09/15/2025 09:00 AM
Notice ID: 1006484
Prior Notice: 1006123
Reqrd Rsp Desc: No response required
Response Date/Time:
Notice Type Desc: Capacity Constraint / Maintenance
Subject: Cove Point Restrictions
Notice Text:
Due to the Planned Service Outage posted on 09/10/2025 (Notice ID #1006479), the following restrictions will be in effect during the
Pleasant Valley Station outage from 09/15/2025 through 10/10/2025. Customers are reminded that these restrictions are subject to change
based on actual operating conditions and available facilities.
For the time period of Gas Days 09/15/2025 – 09/19/2025:
Receipts from Columbia Loudoun (Loc 37001) and EGTS Loudoun (Loc 47001) will flow as scheduled.
Receipts from Transco Pleasant Valley (Loc 45001) will flow as scheduled up to an aggregated 750,000 dekatherms
based on priority of service.
Deliveries to Transco Pleasant Valley (Loc 45001) will flow as scheduled.
Primary Deliveries* to the Cove Point Delivery Locations will flow as scheduled.
Cove Point will deliver, in aggregate, up to 300,000 Dekatherms of Secondary and IT deliveries* across the Cove
Point Delivery Locations.
For Gas Days 09/20/2025 – 09/21/2025:
Receipts from Columbia Loudoun (Loc 37001) and EGTS Loudoun (Loc 47001) will flow as scheduled.
Receipts and Deliveries from/to Transco Pleasant Valley (Loc 45001) will not be scheduled
Primary Deliveries* to the Cove Point Delivery Locations will flow as scheduled.
Cove Point will deliver, in aggregate, up to 20,000 dekatherms of Secondary and IT deliveries* across the Cove
Point Delivery Locations.
For the time period of Gas Days 09/22/2025 – 10/10/2025:
Receipts from Columbia Loudoun (Loc 37001) and EGTS Loudoun (Loc 47001) will flow as scheduled.
Receipts from Transco Pleasant Valley (Loc 45001) will flow as scheduled up to an aggregated 300,000 dekatherms
based on priority of service.
Deliveries to Transco Pleasant Valley (Loc 45001) will flow as scheduled.
Primary Deliveries* to the Cove Point Delivery Locations will flow as scheduled.
Cove Point will deliver, in aggregate, up to 20,000 dekatherms of Secondary and IT deliveries* across the Cove
Point Delivery Locations.
Delivery Location
Name
77060
WGL Willowsford
77010
WGL Centreville
97000
Ox into Possum Pt. Lateral
77020
WGL White Plains
89000
St. Charles M&R
77030
Gardiner Road
88000
Woodville M&R
87000
Chalk Point Plant
77040
WGL Prince Frederick
77050
WGL Patuxent River
10002
CVP Storage Point (ST)
Page 2
*Note that during this outage period, CPL may have limited ability to accept or manage non ratable hourly deliveries.
Please continue to monitor these postings for further updates as estimates are subject to change. Please direct related questions to Ryan
Martin (ryan.martin@bhegts.com or 804.201.8804). Power Generators should direct their requests to the CPL Power Desk.
Critical: Y
Posting Date/Time: 09/10/2025 01:13 PM
Notice Stat Desc: Supersede
Notice Eff Date/Time: 09/15/2025 09:00 AM
Notice ID: 1006484
Prior Notice: 1006123
Reqrd Rsp Desc: No response required
Response Date/Time:
Notice Type Desc: Capacity Constraint / Maintenance
Subject: Cove Point Restrictions
Notice Text:
Due to the Planned Service Outage posted on 09/10/2025 (Notice ID #1006479), the following restrictions will be in effect during the
Pleasant Valley Station outage from 09/15/2025 through 10/10/2025. Customers are reminded that these restrictions are subject to change
based on actual operating conditions and available facilities.
For the time period of Gas Days 09/15/2025 – 09/19/2025:
Receipts from Columbia Loudoun (Loc 37001) and EGTS Loudoun (Loc 47001) will flow as scheduled.
Receipts from Transco Pleasant Valley (Loc 45001) will flow as scheduled up to an aggregated 750,000 dekatherms
based on priority of service.
Deliveries to Transco Pleasant Valley (Loc 45001) will flow as scheduled.
Primary Deliveries* to the Cove Point Delivery Locations will flow as scheduled.
Cove Point will deliver, in aggregate, up to 300,000 Dekatherms of Secondary and IT deliveries* across the Cove
Point Delivery Locations.
For Gas Days 09/20/2025 – 09/21/2025:
Receipts from Columbia Loudoun (Loc 37001) and EGTS Loudoun (Loc 47001) will flow as scheduled.
Receipts and Deliveries from/to Transco Pleasant Valley (Loc 45001) will not be scheduled
Primary Deliveries* to the Cove Point Delivery Locations will flow as scheduled.
Cove Point will deliver, in aggregate, up to 20,000 dekatherms of Secondary and IT deliveries* across the Cove
Point Delivery Locations.
For the time period of Gas Days 09/22/2025 – 10/10/2025:
Receipts from Columbia Loudoun (Loc 37001) and EGTS Loudoun (Loc 47001) will flow as scheduled.
Receipts from Transco Pleasant Valley (Loc 45001) will flow as scheduled up to an aggregated 300,000 dekatherms
based on priority of service.
Deliveries to Transco Pleasant Valley (Loc 45001) will flow as scheduled.
Primary Deliveries* to the Cove Point Delivery Locations will flow as scheduled.
Cove Point will deliver, in aggregate, up to 20,000 dekatherms of Secondary and IT deliveries* across the Cove
Point Delivery Locations.
Delivery Location
Name
77060
WGL Willowsford
77010
WGL Centreville
97000
Ox into Possum Pt. Lateral
77020
WGL White Plains
89000
St. Charles M&R
77030
Gardiner Road
88000
Woodville M&R
87000
Chalk Point Plant
77040
WGL Prince Frederick
77050
WGL Patuxent River
10002
CVP Storage Point (ST)
Page 1
*Note that during this outage period, CPL may have limited ability to accept or manage non ratable hourly deliveries.
Please continue to monitor these postings for further updates as estimates are subject to change. Please direct related questions to Ryan
Martin (ryan.martin@bhegts.com or 804.201.8804). Power Generators should direct their requests to the CPL Power Desk.