Equitrans Gathering Notice 42826
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
07-18-2025 12:35:00
Page 1 of 1
System Wide Notice Detail
TSP Name:
EQMWESTON
TSP:
Post Date/Time:
Fri Jul 18 12:35:00 GMT 2025
Subject:
Pisces Compressor Station Planned Outage Update (High Pressure)(08.06.2025)
Notice Type:
CRITICAL
Notice ID:
42826
Prior Notice:
41986
41986
Notice Status Desc:
Supersede
Critical Desc:
Critical Notice
Notice Eff Date:
07-18-2025
Notice Eff Time:
12:35:00
Notice End Date:
10-31-2025
Notice End Time:
00:00:00
Required Response Indicator Description:
Notice Text:
Update to Notice ID #41986
In conjunction with this downstream maintenance, Pisces Unit #1 will be shut down at 8:00 AM ET on Wednesday August 06, 2025, for an estimated
duration of 16 hours. Pisces Unit #2 will be shut down at 8:00 AM ET Wednesday August 06, 2025, for an estimated duration of 16 hours.
Original Notice (Revised)
EQM Gathering Opco, LLC, an EQM Midstream Partners, LP entity, is providing notice that maintenance is scheduled downstream of the Pisces
Compressor Station on Wednesday August 06, 2025.
In conjunction with this downstream maintenance, Pisces Unit #1 will be shut down at 8:00 AM ET on Wednesday August 06, 2025, for an estimated
duration of 8 hours. Pisces Unit #2 will be shut down at 8:00 AM ET Wednesday August 06, 2025, for an estimated duration of 8 hours.
Customers should adjust nominations accordingly.
Customers should monitor EQM Midstream Partners, LP – Gathering Informational Postings Website for updates to this notice.
Upon completion of the maintenance, Equitrans Midstream will notify customers when they can turn back in-line.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.

System Wide Notice Detail
TSP Name:
EQMWESTON
TSP:
Post Date/Time:
Fri Jul 18 12:35:00 GMT 2025
Subject:
Pisces Compressor Station Planned Outage Update (High Pressure)(08.06.2025)
Notice Type:
CRITICAL
Notice ID:
42826
Prior Notice:
41986
41986
Notice Status Desc:
Supersede
Critical Desc:
Critical Notice
Notice Eff Date:
07-18-2025
Notice Eff Time:
12:35:00
Notice End Date:
10-31-2025
Notice End Time:
00:00:00
Required Response Indicator Description:
Update to Notice ID #41986
In conjunction with this downstream maintenance, Pisces Unit #1 will be shut down at 8:00 AM ET on Wednesday August 06, 2025, for an estimated
duration of 16 hours. Pisces Unit #2 will be shut down at 8:00 AM ET Wednesday August 06, 2025, for an estimated duration of 16 hours.
Original Notice (Revised)
Notice Text:
EQM Gathering Opco, LLC, an EQM Midstream Partners, LP entity, is providing notice that maintenance is scheduled downstream of the Pisces
Compressor Station on Wednesday August 06, 2025.
In conjunction with this downstream maintenance, Pisces Unit #1 will be shut down at 8:00 AM ET on Wednesday August 06, 2025, for an estimated
duration of 8 hours. Pisces Unit #2 will be shut down at 8:00 AM ET Wednesday August 06, 2025, for an estimated duration of 8 hours.
Customers should adjust nominations accordingly.
Customers should monitor EQM Midstream Partners, LP – Gathering Informational Postings Website for updates to this notice.
Upon completion of the maintenance, Equitrans Midstream will notify customers when they can turn back in-line.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.