Equitrans Notice 119579
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
02-06-2025 09:43:00
Page 1 of 2
System Wide Notice Detail
TSP Name:
EQUITRANS LP
TSP:
189569585
Post Date/Time:
Thu Feb 06 09:43:00 GMT 2025
Subject:
Plasma Compressor Station Maintenance 03-04-25 Update 2
Notice Type:
CRITICAL
Notice ID:
119579
Prior Notice:
119222
119222
Notice Status Desc:
Supersede
Critical Desc:
Critical Notice
Notice Eff Date:
02-06-2025
Notice Eff Time:
09:43:00
Notice End Date:
12-31-9000
Notice End Time:
00:00:00
Required Response Indicator Description:
NO RESPONSE REQUIRED
Notice Text:
Equitrans L.P. is providing notice of an update to the Operationally Available Capacity through the Plasma_OVC Meter during upcoming
maintenance at its Plasma Compressor Station.
Equitrans L.P. will be performing maintenance at its Plasma Compressor Station in its Mainline Operational Area 3 beginning March 04, 2025, Gas
Day and continuing through March 06, 2025, Gas Day.
In conjunction with this maintenance, Operationally Available Capacity through the Plasma_OVC Meter will be reduced to the following Net
Delivered Operational Capacities:
March 04, 2025, Gas Day: 720,000 Dths
March 05, 2025, Gas Day: 865,000 Dths
March 06, 2025, Gas Day: 865,000 Dths
Scheduled Quantities will be adjusted to not exceed this amount. This amount is based on projected operating conditions and is subject to change.
02-06-2025 09:43:00
Page 2 of 2
Net Delivered Dths are calculated by netting Receipt and Delivery Scheduled Quantities at the Plasma _OVC Meter listed above.
Nominations will be scheduled in accordance with Section 6.8 of the General Terms and Conditions of Equitrans’ FERC Gas Tariff. Intraday
nomination changes may be permitted should the actual outage timeframe or level of impact differ from the estimates stated in this notification.
In addition, Customers may experience higher than normal pressures on the following pipelines in Mainline Operational Area 3 and Mainline
Operational Area 4: H-302, H-306, H-310, GSF-912, GSF-993, H-557, GSF-604, H-527, H-515, H-518, H-511, H-509, and H-508.
Customers should monitor Equitrans’ Informational Postings Website for updates to this notice and applicable posted Operationally Available
Capacity.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.

System Wide Notice Detail
TSP Name:
EQUITRANS LP
TSP:
189569585
Post Date/Time:
Thu Feb 06 09:43:00 GMT 2025
Subject:
Plasma Compressor Station Maintenance 03-04-25 Update 2
Notice Type:
CRITICAL
Notice ID:
119579
Prior Notice:
119222
119222
Notice Status Desc:
Supersede
Critical Desc:
Critical Notice
Notice Eff Date:
02-06-2025
Notice Eff Time:
09:43:00
Notice End Date:
12-31-9000
Notice End Time:
00:00:00
Required Response Indicator Description:
NO RESPONSE REQUIRED
Equitrans L.P. is providing notice of an update to the Operationally Available Capacity through the Plasma_OVC Meter during upcoming
maintenance at its Plasma Compressor Station.
Equitrans L.P. will be performing maintenance at its Plasma Compressor Station in its Mainline Operational Area 3 beginning March 04, 2025, Gas
Day and continuing through March 06, 2025, Gas Day.
In conjunction with this maintenance, Operationally Available Capacity through the Plasma_OVC Meter will be reduced to the following Net
Delivered Operational Capacities:
March 04, 2025, Gas Day: 720,000 Dths
March 05, 2025, Gas Day: 865,000 Dths
March 06, 2025, Gas Day: 865,000 Dths
Notice Text:
Scheduled Quantities will be adjusted to not exceed this amount. This amount is based on projected operating conditions and is subject to change.
02-06-2025 09:43:00
Page 1 of 2
Net Delivered Dths are calculated by netting Receipt and Delivery Scheduled Quantities at the Plasma _OVC Meter listed above.
Nominations will be scheduled in accordance with Section 6.8 of the General Terms and Conditions of Equitrans’ FERC Gas Tariff. Intraday
nomination changes may be permitted should the actual outage timeframe or level of impact differ from the estimates stated in this notification.
In addition, Customers may experience higher than normal pressures on the following pipelines in Mainline Operational Area 3 and Mainline
Operational Area 4: H-302, H-306, H-310, GSF-912, GSF-993, H-557, GSF-604, H-527, H-515, H-518, H-511, H-509, and H-508.
Customers should monitor Equitrans’ Informational Postings Website for updates to this notice and applicable posted Operationally Available
Capacity.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.
02-06-2025 09:43:00