Guardian Pipeline Notice 1733

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP Name: Guardian Pipeline, L.L.C.

TSP: 03-175-2897

Subject: Planned Service Outage - Joliet Station

Notice Type: Constraint

Critical: Yes

Post Date/Time:: 08/05/2025 01:05 pm

Notice Eff Date/Time: 09/08/2025 09:00 am

NOTICE_END_DATE: 09/10/2025 09:00 am

Notice ID: 1733

Notice Stat Desc: Initiate

Prior Notice: 1733

Reqrd Rsp Desc: No response required

Rsp Date/Time:

Notice Text:

Due to planned maintenance at the Joliet Station, Guardian Pipeline, L.L.C, (GPL) will decrease Joliet ANR receipt, Joliet Vector receipt and delivery, Joliet Alliance receipt, and Joliet Peoples delivery capacity beginning Gas Day Monday, September 08, 2025, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day Tuesday, September 9, 2025.
¿¿
Joliet ANR receipt capacity will be reduced from 1,586,820 Dth to 0 Dth.
Joliet Vector receipt and delivery capacity will be reduced from 1,005,940 Dth to 0 Dth.
Joliet Alliance receipt capacity will be reduced from 1,390,720 Dth to 0 Dth.
Joliet Peoples delivery capacity will be reduced from 196,100 Dth to 0 Dth.
¿
Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of pipeline for the duration of the outage.
¿
GPL does anticipate an impact to firm transportation services. Reservation rate credits will be applied pursuant to GPL's FERC Gas Tariff, General Terms and Conditions, Section 40.

Please contact your Commercial representative with questions.
TSP Name: Guardian Pipeline, L.L.C.

TSP: 03-175-2897

Subject: Planned Service Outage - Joliet Station

Notice Type: Constraint

Critical: Yes

Post Date/Time:: 08/05/2025 01:05 pm

Notice Eff Date/Time: 09/08/2025 09:00 am

NOTICE_END_DATE: 09/10/2025 09:00 am

Notice ID: 1733

Notice Stat Desc: Initiate

Prior Notice: 1733

Reqrd Rsp Desc: No response required

Rsp Date/Time:

Notice Text:

Due to planned maintenance at the Joliet Station, Guardian Pipeline, L.L.C, (GPL) will decrease Joliet ANR receipt, Joliet Vector receipt and delivery, Joliet Alliance receipt, and Joliet Peoples delivery capacity beginning Gas Day Monday, September 08, 2025, Timely Cycle. This capacity constraint is anticipated to be in effect through Gas Day Tuesday, September 9, 2025.
¿¿
Joliet ANR receipt capacity will be reduced from 1,586,820 Dth to 0 Dth.
Joliet Vector receipt and delivery capacity will be reduced from 1,005,940 Dth to 0 Dth.
Joliet Alliance receipt capacity will be reduced from 1,390,720 Dth to 0 Dth.
Joliet Peoples delivery capacity will be reduced from 196,100 Dth to 0 Dth.
¿
Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of pipeline for the duration of the outage.
¿
GPL does anticipate an impact to firm transportation services. Reservation rate credits will be applied pursuant to GPL's FERC Gas Tariff, General Terms and Conditions, Section 40.

Please contact your Commercial representative with questions.