Midwestern Gas Transmission Company Notice 5009
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP Name: Midwestern Gas Transmission Company
TSP: 00-679-2451
Subject: AMENDED: MGT Mainline - Planned Service Outage - US Hwy 50 MAOP
Notice Type: Constraint
Critical: Yes
Post Date/Time:: 08/01/2025 12:45 pm
Notice Eff Date/Time: 09/04/2025 09:00 am
NOTICE_END_DATE: 09/14/2025 09:00 am
Notice ID: 5009
Notice Stat Desc: Supersede
Prior Notice: 5006
Reqrd Rsp Desc: No response required
Rsp Date/Time:
Notice Text:
The planned service outage for MAOP Reconfirmation Hydrotesting has been amended.
The affected segment is near Petersburg CS. Flow South of Wheatland Power and flow North of Grain Processing will be set to 0 during the outage. Wheatland Power will be available for South bound delivery. Grain Processing will be available for North bound delivery.
Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of pipeline for the duration of the outage.
This outage is planned to begin Gas Day Thursday, September 4, 2025, Timely Cycle and is anticipated to be in effect through Gas Day Saturday, September 13, 2025.
MGT does anticipate an impact to firm transportation services. Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.
Please contact your Commercial representative with questions.
-------------------------------------------------------------------------
Prior Notice ID: 5006
Midwestern Gas Transmission Company (MGT) will conduct a planned service outage for MAOP Reconfirmation Hydrotesting on one segment of the pipeline.
The affected segment is near Petersburg CS. Flow South of Wheatland Power and flow North of Ohio Valley will be set to 0 during the outage. Wheatland Power will be available for South bound delivery. Ohio Valley will be available for North bound delivery.
Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of pipeline for the duration of the outage.
This outage is planned to begin Gas Day Thursday, September 4, 2025, Timely Cycle and is anticipated to be in effect through Gas Day Saturday, September 13, 2025.
MGT does anticipate an impact to firm transportation services.¿ Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.¿¿
Please contact your Commercial representative with questions.¿
TSP: 00-679-2451
Subject: AMENDED: MGT Mainline - Planned Service Outage - US Hwy 50 MAOP
Notice Type: Constraint
Critical: Yes
Post Date/Time:: 08/01/2025 12:45 pm
Notice Eff Date/Time: 09/04/2025 09:00 am
NOTICE_END_DATE: 09/14/2025 09:00 am
Notice ID: 5009
Notice Stat Desc: Supersede
Prior Notice: 5006
Reqrd Rsp Desc: No response required
Rsp Date/Time:
Notice Text:
The planned service outage for MAOP Reconfirmation Hydrotesting has been amended.
The affected segment is near Petersburg CS. Flow South of Wheatland Power and flow North of Grain Processing will be set to 0 during the outage. Wheatland Power will be available for South bound delivery. Grain Processing will be available for North bound delivery.
Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of pipeline for the duration of the outage.
This outage is planned to begin Gas Day Thursday, September 4, 2025, Timely Cycle and is anticipated to be in effect through Gas Day Saturday, September 13, 2025.
MGT does anticipate an impact to firm transportation services. Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.
Please contact your Commercial representative with questions.
-------------------------------------------------------------------------
Prior Notice ID: 5006
Midwestern Gas Transmission Company (MGT) will conduct a planned service outage for MAOP Reconfirmation Hydrotesting on one segment of the pipeline.
The affected segment is near Petersburg CS. Flow South of Wheatland Power and flow North of Ohio Valley will be set to 0 during the outage. Wheatland Power will be available for South bound delivery. Ohio Valley will be available for North bound delivery.
Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of pipeline for the duration of the outage.
This outage is planned to begin Gas Day Thursday, September 4, 2025, Timely Cycle and is anticipated to be in effect through Gas Day Saturday, September 13, 2025.
MGT does anticipate an impact to firm transportation services.¿ Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.¿¿
Please contact your Commercial representative with questions.¿
TSP Name: Midwestern Gas Transmission Company
TSP: 00-679-2451
Subject: AMENDED: MGT Mainline - Planned Service Outage - US Hwy 50 MAOP
Notice Type: Constraint
Critical: Yes
Post Date/Time:: 08/01/2025 12:45 pm
Notice Eff Date/Time: 09/04/2025 09:00 am
NOTICE_END_DATE: 09/14/2025 09:00 am
Notice ID: 5009
Notice Stat Desc: Supersede
Prior Notice: 5006
Reqrd Rsp Desc: No response required
Rsp Date/Time:
Notice Text:
The planned service outage for MAOP Reconfirmation Hydrotesting has been amended.
The affected segment is near Petersburg CS. Flow South of Wheatland Power and flow North of Grain Processing will be set to 0 during the outage. Wheatland Power will be available for South bound delivery. Grain Processing will be available for North bound delivery.
Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of pipeline for the duration of the outage.
This outage is planned to begin Gas Day Thursday, September 4, 2025, Timely Cycle and is anticipated to be in effect through Gas Day Saturday, September 13, 2025.
MGT does anticipate an impact to firm transportation services. Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.
Please contact your Commercial representative with questions.
-------------------------------------------------------------------------
Prior Notice ID: 5006
Midwestern Gas Transmission Company (MGT) will conduct a planned service outage for MAOP Reconfirmation Hydrotesting on one segment of the pipeline.
The affected segment is near Petersburg CS. Flow South of Wheatland Power and flow North of Ohio Valley will be set to 0 during the outage. Wheatland Power will be available for South bound delivery. Ohio Valley will be available for North bound delivery.
Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of pipeline for the duration of the outage.
This outage is planned to begin Gas Day Thursday, September 4, 2025, Timely Cycle and is anticipated to be in effect through Gas Day Saturday, September 13, 2025.
MGT does anticipate an impact to firm transportation services.¿ Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.¿¿
Please contact your Commercial representative with questions.¿
TSP: 00-679-2451
Subject: AMENDED: MGT Mainline - Planned Service Outage - US Hwy 50 MAOP
Notice Type: Constraint
Critical: Yes
Post Date/Time:: 08/01/2025 12:45 pm
Notice Eff Date/Time: 09/04/2025 09:00 am
NOTICE_END_DATE: 09/14/2025 09:00 am
Notice ID: 5009
Notice Stat Desc: Supersede
Prior Notice: 5006
Reqrd Rsp Desc: No response required
Rsp Date/Time:
Notice Text:
The planned service outage for MAOP Reconfirmation Hydrotesting has been amended.
The affected segment is near Petersburg CS. Flow South of Wheatland Power and flow North of Grain Processing will be set to 0 during the outage. Wheatland Power will be available for South bound delivery. Grain Processing will be available for North bound delivery.
Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of pipeline for the duration of the outage.
This outage is planned to begin Gas Day Thursday, September 4, 2025, Timely Cycle and is anticipated to be in effect through Gas Day Saturday, September 13, 2025.
MGT does anticipate an impact to firm transportation services. Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.
Please contact your Commercial representative with questions.
-------------------------------------------------------------------------
Prior Notice ID: 5006
Midwestern Gas Transmission Company (MGT) will conduct a planned service outage for MAOP Reconfirmation Hydrotesting on one segment of the pipeline.
The affected segment is near Petersburg CS. Flow South of Wheatland Power and flow North of Ohio Valley will be set to 0 during the outage. Wheatland Power will be available for South bound delivery. Ohio Valley will be available for North bound delivery.
Please be advised that full haul transportation will not be available. Nominations will not be accepted for flow through this segment of pipeline for the duration of the outage.
This outage is planned to begin Gas Day Thursday, September 4, 2025, Timely Cycle and is anticipated to be in effect through Gas Day Saturday, September 13, 2025.
MGT does anticipate an impact to firm transportation services.¿ Demand charge credits will be applied pursuant to MGT's FERC Gas Tariff, General Terms and Conditions, Section 37.¿¿
Please contact your Commercial representative with questions.¿