TSP Name: OkTex Pipeline Company, L.L.C.
TSP: 80-002-2246
Subject: Norteno 5 - Planned Maintenance - El Paso Anthony/El Paso Canutillo
Notice Type: Maint
Critical: Yes
Post Date/Time:: 07/28/2025 05:04 pm
Notice Eff Date/Time: 07/28/2025 05:04 pm
NOTICE_END_DATE: 08/05/2025 05:00 pm
Notice ID: 565
Notice Stat Desc: Initiate
Prior Notice: 565
Reqrd Rsp Desc: No response required
Rsp Date/Time:
Notice Text:
Good Afternoon,
OKTEX has a planned maintenance on the pipeline that serves receipt locations: El Paso Anthony & El Paso Canutillo, along with delivery locations: PNM Anthony & PNM Canutillo taking place on 7/28/25, beginning at 7:00 A.M., through 8/5/2025, ending at 5:00 P.M., for a total of 9 days.
During the days of the outage, the above impacted location will be shut in and reduced to 0 Dth. of transport capacity, resulting in an impact to Firm and/or Interruptible service until the work is complete. Nominations will need to be reduced to match the capacity to rate out for each gas day.
Please share this communication with your Marketing team and let us know of any questions or concerns.
TSP: 80-002-2246
Subject: Norteno 5 - Planned Maintenance - El Paso Anthony/El Paso Canutillo
Notice Type: Maint
Critical: Yes
Post Date/Time:: 07/28/2025 05:04 pm
Notice Eff Date/Time: 07/28/2025 05:04 pm
NOTICE_END_DATE: 08/05/2025 05:00 pm
Notice ID: 565
Notice Stat Desc: Initiate
Prior Notice: 565
Reqrd Rsp Desc: No response required
Rsp Date/Time:
Notice Text:
Good Afternoon,
OKTEX has a planned maintenance on the pipeline that serves receipt locations: El Paso Anthony & El Paso Canutillo, along with delivery locations: PNM Anthony & PNM Canutillo taking place on 7/28/25, beginning at 7:00 A.M., through 8/5/2025, ending at 5:00 P.M., for a total of 9 days.
During the days of the outage, the above impacted location will be shut in and reduced to 0 Dth. of transport capacity, resulting in an impact to Firm and/or Interruptible service until the work is complete. Nominations will need to be reduced to match the capacity to rate out for each gas day.
Please share this communication with your Marketing team and let us know of any questions or concerns.
TSP Name: OkTex Pipeline Company, L.L.C.
TSP: 80-002-2246
Subject: Norteno 5 - Planned Maintenance - El Paso Anthony/El Paso Canutillo
Notice Type: Maint
Critical: Yes
Post Date/Time:: 07/28/2025 05:04 pm
Notice Eff Date/Time: 07/28/2025 05:04 pm
NOTICE_END_DATE: 08/05/2025 05:00 pm
Notice ID: 565
Notice Stat Desc: Initiate
Prior Notice: 565
Reqrd Rsp Desc: No response required
Rsp Date/Time:
Notice Text:
Good Afternoon,
OKTEX has a planned maintenance on the pipeline that serves receipt locations: El Paso Anthony & El Paso Canutillo, along with delivery locations: PNM Anthony & PNM Canutillo taking place on 7/28/25, beginning at 7:00 A.M., through 8/5/2025, ending at 5:00 P.M., for a total of 9 days.
During the days of the outage, the above impacted location will be shut in and reduced to 0 Dth. of transport capacity, resulting in an impact to Firm and/or Interruptible service until the work is complete. Nominations will need to be reduced to match the capacity to rate out for each gas day.
Please share this communication with your Marketing team and let us know of any questions or concerns.
TSP: 80-002-2246
Subject: Norteno 5 - Planned Maintenance - El Paso Anthony/El Paso Canutillo
Notice Type: Maint
Critical: Yes
Post Date/Time:: 07/28/2025 05:04 pm
Notice Eff Date/Time: 07/28/2025 05:04 pm
NOTICE_END_DATE: 08/05/2025 05:00 pm
Notice ID: 565
Notice Stat Desc: Initiate
Prior Notice: 565
Reqrd Rsp Desc: No response required
Rsp Date/Time:
Notice Text:
Good Afternoon,
OKTEX has a planned maintenance on the pipeline that serves receipt locations: El Paso Anthony & El Paso Canutillo, along with delivery locations: PNM Anthony & PNM Canutillo taking place on 7/28/25, beginning at 7:00 A.M., through 8/5/2025, ending at 5:00 P.M., for a total of 9 days.
During the days of the outage, the above impacted location will be shut in and reduced to 0 Dth. of transport capacity, resulting in an impact to Firm and/or Interruptible service until the work is complete. Nominations will need to be reduced to match the capacity to rate out for each gas day.
Please share this communication with your Marketing team and let us know of any questions or concerns.