Adding proxy2: 8644 Tennessee Gas Pipeline Notice 395025 - API PipeRiv

Currently viewing the dev server.

Tennessee Gas Pipeline Notice 395025

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  CAPACITY CONSTRAINT Notice Type Desc (2):  SEGMENTS
Notice Eff Date/Time:  06/27/2025 6:58:56AM Notice End Date/Time:  06/28/2025 9:00:00am
Post Date/Time:  6/27/2025 6:58:56 AM Notice ID: 395025
Reqrd Rsp:  1 Rsp Date:  06/27/2025
Notice Stat Desc:  SUPERSEDE Prior Notice:  394954
Subject:  ANT PIP RESTRICTION UPDATE #4 EFF 6-28
Notice Text:

ANTICIPATED PRIMARY IN THE PATH RESTRICTIONS UPDATE #3 EFFECTIVE 6-28-2025

 

Based on new information, Tennessee now anticipates scheduling Primary In the Path ("PIP") transports to no less than the percentage of firm contracts pathed through the following segment.  This notice supersedes the previous notice posted earlier on June 19, 2025 (Notice Identifier #394954).

 

STA 860 500 Line (Segment 548 BH) – effective Timely Cycle for the Gas Day of Saturday, June 28, 2025 and until further notice - no less than 60% of contract MDQ

 

The stated scheduling percentages are based upon the current level of firm capacity contracted for during this restriction and is subject to change based upon operational conditions and Shipper utilization.

 

Please contact your Account Director or Scheduling Representative if you have any questions.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  CAPACITY CONSTRAINT Notice Type Desc (2):  SEGMENTS
Notice Eff Date/Time:  06/27/2025 6:58:56AM Notice End Date/Time:  06/28/2025 9:00:00am
Post Date/Time:  6/27/2025 6:58:56 AM Notice ID: 395025
Reqrd Rsp:  1 Rsp Date:  06/27/2025
Notice Stat Desc:  SUPERSEDE Prior Notice:  394954
Subject:  ANT PIP RESTRICTION UPDATE #4 EFF 6-28
Notice Text:

ANTICIPATED PRIMARY IN THE PATH RESTRICTIONS UPDATE #3 EFFECTIVE 6-28-2025

 

Based on new information, Tennessee now anticipates scheduling Primary In the Path ("PIP") transports to no less than the percentage of firm contracts pathed through the following segment.  This notice supersedes the previous notice posted earlier on June 19, 2025 (Notice Identifier #394954).

 

STA 860 500 Line (Segment 548 BH) – effective Timely Cycle for the Gas Day of Saturday, June 28, 2025 and until further notice - no less than 60% of contract MDQ

 

The stated scheduling percentages are based upon the current level of firm capacity contracted for during this restriction and is subject to change based upon operational conditions and Shipper utilization.

 

Please contact your Account Director or Scheduling Representative if you have any questions.