Tennessee Gas Pipeline Notice 395089
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
Notice Eff Date/Time: 07/03/2025 2:46:27PM | Notice End Date/Time: 07/04/2025 9:00:00am |
Post Date/Time: 7/3/2025 2:46:27 PM | Notice ID: 395089 |
Reqrd Rsp: 1 | Rsp Date: 07/03/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: RESTRICTIONS FOR 07-04-2025 TIMELY CYCLE |
Effective Timely Cycle (9:00) for the gas day of Friday, July 04, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· ETP/TGP Wharton County Transport Ex Delivery Meter (Pin 411911) - through 100% of IT deliveries due to displacement gas unavailable for backhaul; 5,474 Dths
· KMTEJAS/TGP Jackson (Ganado) Delivery Meter (Pin 49803) - through approx 59% of IT due to operational concerns; 34,874 Dths
· TGP/SNG Bear Creek Injection Bienvi Delivery Meter (Pin 405367) - through 100% of SOP due to operational concerns; 5,000 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SIPps due to operational concerns; 4,623 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 84% of SIPss due to nominations in excess of operational capacity; 119,965 Dths
SEGMENT RESTRICTIONS
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP due to nominations in excess of operational capacity; 50,000 Dths
· STA 523 West (Segment 516 FH) - through approx 100% of SOP due to nominations in excess of operational capacity; 39,888 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 31,761 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to nominations in excess of operational capacity; 436,053 Dths
· MLV 314 East (Segment 314 BH) - through approx 95% of SOP due to nominations in excess of operational capacity; 674,872 Dths
· STA 315 (Segment 315 BH) - through approx 86% of SOP due to nominations in excess of operational capacity; 681,275 Dths
· STA 317 (Segment 317 BH) - through approx 50% of SOP due to nominations in excess of operational capacity; 67,812 Dths
· STA 321 (Segment 321 FH) - through approx 43% of SOP due to nominations in excess of operational capacity; 439,513 Dths
· MLV 330 (Segment 324 FH) - through approx 26% of SOP due to nominations in excess of operational capacity; 139,337 Dths
· MLV 355 (Segment 355 BH) - through 100% of SOP due to operational concerns; 25,000 Dths
· STA 224 (Segment 224 BH) - through approx 60% of SOP due to nominations in excess of operational capacity; 82,426 Dths
· Z5hc North (Segment 299 FH) - through approx 80% of SOP due to nominations in excess of operational capacity; 714,083 Dths
· STA 245 (Segment 245 FH) - through approx 86% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 893,419 Dths
· STA 249 (Segment 249 FH) - through approx 63% of SOP due to nominations in excess of operational capacity; 420,008 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 21% of SOP due to nominations in excess of operational capacity; 48,359 Dths
· MLV 273 (Segment 284 FH) - through approx 99% of SOP due to nominations in excess of operational capacity; 466,504 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
Notice Eff Date/Time: 07/03/2025 2:46:27PM | Notice End Date/Time: 07/04/2025 9:00:00am |
Post Date/Time: 7/3/2025 2:46:27 PM | Notice ID: 395089 |
Reqrd Rsp: 1 | Rsp Date: 07/03/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: RESTRICTIONS FOR 07-04-2025 TIMELY CYCLE |
Effective Timely Cycle (9:00) for the gas day of Friday, July 04, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· ETP/TGP Wharton County Transport Ex Delivery Meter (Pin 411911) - through 100% of IT deliveries due to displacement gas unavailable for backhaul; 5,474 Dths
· KMTEJAS/TGP Jackson (Ganado) Delivery Meter (Pin 49803) - through approx 59% of IT due to operational concerns; 34,874 Dths
· TGP/SNG Bear Creek Injection Bienvi Delivery Meter (Pin 405367) - through 100% of SOP due to operational concerns; 5,000 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SIPps due to operational concerns; 4,623 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 84% of SIPss due to nominations in excess of operational capacity; 119,965 Dths
SEGMENT RESTRICTIONS
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP due to nominations in excess of operational capacity; 50,000 Dths
· STA 523 West (Segment 516 FH) - through approx 100% of SOP due to nominations in excess of operational capacity; 39,888 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 31,761 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to nominations in excess of operational capacity; 436,053 Dths
· MLV 314 East (Segment 314 BH) - through approx 95% of SOP due to nominations in excess of operational capacity; 674,872 Dths
· STA 315 (Segment 315 BH) - through approx 86% of SOP due to nominations in excess of operational capacity; 681,275 Dths
· STA 317 (Segment 317 BH) - through approx 50% of SOP due to nominations in excess of operational capacity; 67,812 Dths
· STA 321 (Segment 321 FH) - through approx 43% of SOP due to nominations in excess of operational capacity; 439,513 Dths
· MLV 330 (Segment 324 FH) - through approx 26% of SOP due to nominations in excess of operational capacity; 139,337 Dths
· MLV 355 (Segment 355 BH) - through 100% of SOP due to operational concerns; 25,000 Dths
· STA 224 (Segment 224 BH) - through approx 60% of SOP due to nominations in excess of operational capacity; 82,426 Dths
· Z5hc North (Segment 299 FH) - through approx 80% of SOP due to nominations in excess of operational capacity; 714,083 Dths
· STA 245 (Segment 245 FH) - through approx 86% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 893,419 Dths
· STA 249 (Segment 249 FH) - through approx 63% of SOP due to nominations in excess of operational capacity; 420,008 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 21% of SOP due to nominations in excess of operational capacity; 48,359 Dths
· MLV 273 (Segment 284 FH) - through approx 99% of SOP due to nominations in excess of operational capacity; 466,504 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.