TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 07/29/2025
Notice Eff Time: 10:25:27 CDT
Notice End Date:
Notice End Time:
Notice ID: 15905621
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 07/29/2025
Post Time: 10:25:27 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Unplanned Maintenance Station 115 MU3 Planned Outage and Maintenance Summary

Transco will be performing unplanned maintenance at Station 115 due to equipment failure on Main Unit 3 that requires immediate action. The current schedule for repairs is effective immediately July 29, 2025 through TBD. Transco will provide an updated completion date as soon as it becomes available.

During this period of unplanned maintenance, non-secondary reverse path (NSRP), secondary FT, and interruptible (IT) transactions moving south to north through the location may not be available.

Transco will be required to manage transportation services moving south to north through the TSB location listed below. The total quantity available will be contingent on system conditions during the maintenance period and is anticipated to be initially limited to the quantities indicated below. Transactions moving north to south through this location will not be impacted.

The receipt-based Throughput Section Boundary (TSB) at Mainline MP 1031 will be used to manage capacity availability, including any required changes to the expected total quantities available during this unplanned work indicated below. An updated Market and Production Area constraint notice will include the location and the available quantity of primary-firm transportation services during the indicated periods. 

 

TSB Name – Location  

Location ID  

Flow Direction  

Design Capacity (Mdt/d)  

Total Quantity Available (Mdt/d) 

Mainline MP 1031

9013083 

South to North  

4,524

See Below

 

 

Pipeline Maintenance

Estimated Outage

Total Quantity Available Mdt/d

% Cuts (Primary)Potential Shipper Impact (Based on Historical Utilization)   

Unplanned Maintenance MU3

July 29 – TBD

 3,450

0-5%

 

*% Cuts (Primary) is an estimate of the impact to primary firm shippers based on historical utilization and anticipated volumes during the time of constraint. These amounts are subject to change based on actual nominated firm volumes and changes in the amount of available capacity.

Based on current and historical utilization, impacts to Primary Transportation are unlikely, however, impacts to Non-Primary Transportation are anticipated.