| Type | Posted | Effective | End | Identifier | Status | Subject | Response |
|---|---|---|---|---|---|---|---|
| Operational Flow Order Other Pipeline Conditions | 02/21/25 | 02/22/25 | 10125 | Eastern Shore Pipeline Conditions - OFO Termination Effective 02222025 | |||
| Capacity Constraint Operational Flow Order Other Pipeline Conditions | 02/18/25 | 02/17/25 | 10115 | Eastern Shore Pipeline Conditions - OFO Effective 02-17-25 Reminder | |||
| Capacity Constraint Operational Flow Order Other Pipeline Conditions | 02/14/25 | 02/17/25 | 10108 | Eastern Shore Pipeline Conditions - OFO Effective 02-17-25 | |||
| Operational Flow Order Other Pipeline Conditions | 01/24/25 | 01/25/25 | 10054 | Eastern Shore Pipeline Conditions - OFO Termination Effective 01252025 | |||
| Operational Flow Order Other Pipeline Conditions | 01/22/25 | 01/22/25 | 10047 | Eastern Shore Pipe25line Conditions - OFO UPDATE Effective 01-23-25 | |||
| Capacity Constraint Operational Flow Order Other Pipeline Conditions | 01/17/25 | 01/20/25 | 10037 | Eastern Shore Pipeline Conditions - OFO Effective 01-20-25 | |||
| Other | 07/19/24 | 07/19/24 | 9733 | Critical Notices | |||
| Other | 07/19/24 | 07/19/24 | 9731 | Critical Notices | |||
| Other | 04/19/24 | 04/19/24 | 9627 | Downtime Due to System Maintenance-Texas Eastern (TE) effective 04-19-24Reminder | |||
| Other | 04/10/24 | 04/19/24 | 04/21/24 | 9610 | Downtime Due to System Maintenance-Texas Eastern (TE) effective 04-19-24 | ||
| Operational Flow Order | 01/19/24 | 01/22/24 | 9413 | Eastern Shore Pipeline Conditions - OFO Termination Effective 01222024 | |||
| Operational Flow Order | 01/12/24 | 01/15/24 | 9394 | Eastern Shore Pipeline Conditions - Operational Flow Order Effective 011524 | |||
| Operational Flow Order | 02/06/23 | 02/06/23 | 8850 | Eastern Shore Pipeline Conditions - OFO Termination Effective 02062023 | |||
| Operational Flow Order | 02/06/23 | 02/06/23 | 8847 | Eastern Shore Pipeline Conditions - OFO Termination Effective 02062023 | |||
| Operational Flow Order | 02/02/23 | 02/03/23 | 8838 | Eastern Shore Pipeline Conditions - Operational Flow Order Effective 020323 | |||
| Operational Flow Order | 01/05/23 | 01/05/23 | 8772 | Eastern Shore Pipeline Conditions - OFO Termination Effective 01052023 | |||
| Operational Flow Order | 12/22/22 | 12/23/22 | 8743 | Eastern Shore Pipeline Conditions - Operational Flow Order Effective 122322 | |||
| Operational Alert Operational Flow Order Other Scheduling Alert | 01/30/22 | 01/30/22 | 8226 | Eastern Shore Pipeline Conditions - OFO Termination Effective 01302022 | |||
| Operational Alert Operational Flow Order Other Pipeline Conditions Scheduling Alert | 01/28/22 | 01/29/22 | 8220 | Eastern Shore Pipeline Conditions - Operational Flow Order Effective 012922 | |||
| Customer Services Update Operational Alert Operational Flow Order Other Over-Under Performance Pipeline Conditions Scheduling Alert | 01/22/22 | 01/22/22 | 8205 | Eastern Shore Pipeline Conditions - OFO Termination Effective 01222022 | |||
| Operational Alert Operational Flow Order Other Pipeline Conditions Scheduling Alert | 01/20/22 | 01/21/22 | 8199 | Eastern Shore Pipeline Conditions - Operational Flow Order Effective 012122 | |||
| Customer Services Update Operational Alert Operational Flow Order Other Pipeline Conditions Scheduling Alert | 01/15/22 | 01/15/22 | 8187 | Eastern Shore Pipeline Conditions - OFO Termination Effective 01162022 | |||
| Other | 09/02/21 | 09/02/21 | 7939 | Critical Notices | |||
| Other | 09/02/21 | 09/02/21 | 7938 | Critical Notices | |||
| Operational Flow Order Storage | 05/12/21 | 05/12/21 | 7819 | Eastern Shore Pipeline Conditions - OFO Termination Effective 05132021 | |||
| Operational Flow Order Storage | 04/28/21 | 04/28/21 | 7802 | Eastern Shore Pipeline Conditions - Operational Flow Order Effective 05012021 | |||
| Other | 11/30/20 | 12/14/20 | 7458 | Planned Service Outage - Update | |||
| Pipeline Conditions | 07/28/20 | 07/28/20 | 08/14/20 | 7284 | Transco Receipt Point Impacts due to Transco Planned Outage (Job #276 | ||
| Customer Services Update Other | 10/09/19 | 10/09/19 | 6750 | Companywide Communications Outage | |||
| Planned Service Outage | 02/15/19 | 02/21/19 | 02/22/19 | 6421 | Planned Service Outage at ESNG Parkesburg interconnect with Transco Eff022119 | ||
| Operational Flow Order | 02/01/19 | 02/02/19 | 6385 | Eastern Shore Pipeline Conditions – Termination of Operational Flow Order (OFO) | |||
| Operational Flow Order | 01/29/19 | 01/30/19 | 6373 | Eastern Shore Pipeline Conditions Operational Flow Order Effective 013019 | |||
| Operational Flow Order | 01/22/19 | 01/23/19 | 6356 | Eastern Shore Pipeline Conditions – Termination of Operational Flow Order (OFO) | |||
| Operational Flow Order | 01/18/19 | 01/20/19 | 6348 | Eastern Shore Pipeline Conditions - Operational Flow Order Effective 012019 | |||
| Other | 12/02/08 | 12/05/08 | 15 | Imbalance Operational Flow Order (OFO) - Transco |