Iroquois Gas Transmission System Notice 7010
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Capacity Constraint
Effective Timely Cycle, Gas Day November 24, 2025, nominations are sealed from all increases through the following locations:
- MLV-14
- Brookfield Interconnect with Algonquin Gas Transmission.
In addition, the following capacity has been reduced:
- MLV-14 – IT and ER/ED nominations forward-haul through mainline valve 14 are reduced by 100% and Secondary Out of Path (SOP) nominations forward-haul through mainline valve 14 are reduced by 75%.
- Brookfield Interconnect – IT receipt nominations at the Brookfield Interconnect are reduced by 100% and Secondary receipt nominations at the Brookfield Interconnect are reduced by 76%.
If you have any further questions, please contact the Iroquois Scheduling or Gas Control Group.
End date 11/25/2025 09:00 AM CCT
Capacity Constraint
Effective Timely Cycle, Gas Day November 24, 2025, nominations are sealed from all increases through the following locations:
- MLV-14
- Brookfield Interconnect with Algonquin Gas Transmission.
In addition, the following capacity has been reduced:
- MLV-14 – IT and ER/ED nominations forward-haul through mainline valve 14 are reduced by 100% and Secondary Out of Path (SOP) nominations forward-haul through mainline valve 14 are reduced by 75%.
- Brookfield Interconnect – IT receipt nominations at the Brookfield Interconnect are reduced by 100% and Secondary receipt nominations at the Brookfield Interconnect are reduced by 76%.
If you have any further questions, please contact the Iroquois Scheduling or Gas Control Group.
End date 11/25/2025 09:00 AM CCT