Kinetica Partners Notice 1466
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
November 9, 2023
Bluewater West Leg November Pigging
On November 14th, Kinetica Energy Express will perform maintenance pigging on the West Leg of the
Bluewater system. In order to complete this pigging, Kinetica will need to reverse the system’s normal
direction of flow. As a result, all production points on the Bluewater system will be directed north on the
West Leg into the Pecan Island station.
All production listed below will be required to shift nominations from delivery points downstream of the
Cocodrie plant to points north of Pecan Island for four days from November 14th through November17th.
The available delivery points are as follows:
•
Meter 024012 – EnLink/LIG Gueydan
•
Meter 024016 – Egan Gap Arrowhead (Harvest/Kaplan)
For questions regarding facilities or operations, please contact Rae Donaldson at (985) 223-6149.
For scheduling questions, please contact the Scheduling team at scheduling@kineticallc.com.
Customers are strongly advised to monitor the EBB for updates.
Meter
Number
Description
11210
SMI 27A
11366
VR 245E
11692
SMI 106A
12428
SMI 72
12435
SMI 076
12880
VR 214
12881
VR 229A
14007
SMI 71F
14015
SMI 58G
14017
VR 78
18003
Hilcorp Station 600
Meter
Number
Description
11069
EI 257D
11180
SS 198H
11182
SS 182C
11691
SS 181B
11802
SS 198J
12644
SS 110A
12838
EI 224G
14011
SS 182C
14012
SS 193A
18036
SMI 99
Bluewater West Leg November Pigging
On November 14th, Kinetica Energy Express will perform maintenance pigging on the West Leg of the
Bluewater system. In order to complete this pigging, Kinetica will need to reverse the system’s normal
direction of flow. As a result, all production points on the Bluewater system will be directed north on the
West Leg into the Pecan Island station.
All production listed below will be required to shift nominations from delivery points downstream of the
Cocodrie plant to points north of Pecan Island for four days from November 14th through November17th.
The available delivery points are as follows:
•
Meter 024012 – EnLink/LIG Gueydan
•
Meter 024016 – Egan Gap Arrowhead (Harvest/Kaplan)
Meter
Meter
Number
Description
Description
Number
11210
SMI 27A
11069
EI 257D
11366
VR 245E
11180
SS 198H
11692
SMI 106A
11182
SS 182C
12428
SMI 72
11691
SS 181B
12435
SMI 076
11802
SS 198J
12880
VR 214
12644
SS 110A
12881
VR 229A
12838
EI 224G
14007
SMI 71F
14011
SS 182C
14015
SMI 58G
14012
SS 193A
14017
VR 78
18036
SMI 99
18003
Hilcorp Station 600
For questions regarding facilities or operations, please contact Rae Donaldson at (985) 223-6149.
For scheduling questions, please contact the Scheduling team at scheduling@kineticallc.com.
Customers are strongly advised to monitor the EBB for updates.