Notice Type
Capacity Constraint

Effective Start Date Time
05/28/2025 10:00 pm

Subject
NGTL Service (EGAT IT-D)

Notice Text

NGTL Service (EGAT IT-D)

USJR: N/A

WGAT: The planned maintenance on the Burton Creek Compressor Station (19717034) is ongoing, service allowable at Alberta-BC and Alberta Montana Border will remain at 0% IT-D and partial FT-D until further notice.

EGAT: Due to upcoming planned maintenance on the NPS 42 Foothills Pipeline Zone 6 (19700927) and Crawling Valley Compressor Station (19724789), service allowable will transition from 100% IT-D and 100% FT-D to 0% IT-D and 100% FT-D for segments 15, 16, 17, 18, 19, 20, 23, partial 21 and partial 28 (lower EGAT).

Local Area/Location: N/A

New Information

Updated Information

 

Current and upcoming outages

Outage ID

Start

End

 Facility/Outage Name

Facility Type/Scope

Outage Type

Area of Impact

19717034

May 27, 2025

June 1, 2025

Burton Creek

Compressor Station Maintenance

Planned

WGAT

19700927

June 02, 2025

June 07, 2025

NPS 42 Foothills Pipeline Zone 6

Pipeline Maintenance

Planned

EGAT

19724789

June 02, 2025

June 15, 2025

Crawling Valley

Compressor Station Maintenance

Planned

EGAT

 

Upstream James River Receipt Area

Effective:

May 16, 2025 at 08:00 MST

IT Allowable: 20%

IT-R

  IT-S (receipt)

 

 

Expected End:

Until further notice

FT Allowable: 100%

FT-R

FT-P

 

 

 

Interconnects:

  Aitken Creek, Groundbirch East, Gordondale

Segments:

Segments 2, 3, 4, and partial 7 (Upstream of Latornell)

 

West Gate Delivery Area

Effective:

May 27, 2025 at 08:00 MST

IT Allowable: 0%

IT-D

 

 

 

 

Expected End:

Until further notice

FT Allowable: Partial

FT-P

FT-D1

FT-D2

STFT

 

Interconnects:

  Alberta-B.C. Border and Alberta Montana Border

Segments:

  Partial 21 (Alberta-B.C. Border and Alberta Montana Border)

 

East Gate Delivery Area

Effective:

February 12, 2025 at 08:00 MST

IT Allowable: 100%

IT-D

  IT-S (delivery)

 

 

Expected End:

June 02, 2025 at 08:00 MST

FT Allowable: 100%

FT-P

FT-D1

FT-D2

STFT

 

Interconnects:

  Aeco C, Carbon, Chancellor, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Cold Lake, Warwick SE

Segments:

6, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24, partial 21 and partial 28 (Greater EGAT)

Effective:

June 02, 2025 at 08:00 MST

IT Allowable: 0%

IT-D

   IT-S (delivery)

 

 

Expected End:

Until further notice

FT Allowable: 100%

FT-P

FT-D1

FT-D2

 STFT

 

Interconnects:

  Aeco C, Carbon, Chancellor, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Warwick SE

Segments:

  15, 16, 17, 18, 19, 20, 23, partial 21, and partial 28 (Lower EGAT)

 

Local Area/Location

N/A

 

If there is an overlap between Local Area/Location and Upstream James River Receipt Area, West Gate Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT Allowable will be in effect. The details in this bulletin supersede any previously published information and will be reflected and maintained in the next release of the Daily Operating Plan.

NGTL System - Segment Codes & Project Areas Map

NGTL System - Operational Areas Map



Notice Type
Capacity Constraint

Effective Start Date Time
05/28/2025 10:00 pm

Subject
NGTL Service (EGAT IT-D)

Notice Text

NGTL Service (EGAT IT-D)

USJR: N/A

WGAT: The planned maintenance on the Burton Creek Compressor Station (19717034) is ongoing, service allowable at Alberta-BC and Alberta Montana Border will remain at 0% IT-D and partial FT-D until further notice.

EGAT: Due to upcoming planned maintenance on the NPS 42 Foothills Pipeline Zone 6 (19700927) and Crawling Valley Compressor Station (19724789), service allowable will transition from 100% IT-D and 100% FT-D to 0% IT-D and 100% FT-D for segments 15, 16, 17, 18, 19, 20, 23, partial 21 and partial 28 (lower EGAT).

Local Area/Location: N/A

New Information

Updated Information

 

Current and upcoming outages

Outage ID

Start

End

 Facility/Outage Name

Facility Type/Scope

Outage Type

Area of Impact

19717034

May 27, 2025

June 1, 2025

Burton Creek

Compressor Station Maintenance

Planned

WGAT

19700927

June 02, 2025

June 07, 2025

NPS 42 Foothills Pipeline Zone 6

Pipeline Maintenance

Planned

EGAT

19724789

June 02, 2025

June 15, 2025

Crawling Valley

Compressor Station Maintenance

Planned

EGAT

 

Upstream James River Receipt Area

Effective:

May 16, 2025 at 08:00 MST

IT Allowable: 20%

IT-R

  IT-S (receipt)

 

 

Expected End:

Until further notice

FT Allowable: 100%

FT-R

FT-P

 

 

 

Interconnects:

  Aitken Creek, Groundbirch East, Gordondale

Segments:

Segments 2, 3, 4, and partial 7 (Upstream of Latornell)

 

West Gate Delivery Area

Effective:

May 27, 2025 at 08:00 MST

IT Allowable: 0%

IT-D

 

 

 

 

Expected End:

Until further notice

FT Allowable: Partial

FT-P

FT-D1

FT-D2

STFT

 

Interconnects:

  Alberta-B.C. Border and Alberta Montana Border

Segments:

  Partial 21 (Alberta-B.C. Border and Alberta Montana Border)

 

East Gate Delivery Area

Effective:

February 12, 2025 at 08:00 MST

IT Allowable: 100%

IT-D

  IT-S (delivery)

 

 

Expected End:

June 02, 2025 at 08:00 MST

FT Allowable: 100%

FT-P

FT-D1

FT-D2

STFT

 

Interconnects:

  Aeco C, Carbon, Chancellor, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Cold Lake, Warwick SE

Segments:

6, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24, partial 21 and partial 28 (Greater EGAT)

Effective:

June 02, 2025 at 08:00 MST

IT Allowable: 0%

IT-D

   IT-S (delivery)

 

 

Expected End:

Until further notice

FT Allowable: 100%

FT-P

FT-D1

FT-D2

 STFT

 

Interconnects:

  Aeco C, Carbon, Chancellor, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Warwick SE

Segments:

  15, 16, 17, 18, 19, 20, 23, partial 21, and partial 28 (Lower EGAT)

 

Local Area/Location

N/A

 

If there is an overlap between Local Area/Location and Upstream James River Receipt Area, West Gate Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT Allowable will be in effect. The details in this bulletin supersede any previously published information and will be reflected and maintained in the next release of the Daily Operating Plan.