NGTL Notice 3374724178
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Capacity Constraint
Effective Start Date Time
09/17/2025 10:22 pm
Subject
NGTL Service (NEDA FT-D)
Notice Text
NGTL Service (NEDA FT-D)
USJR: N/A
WGAT: N/A
EGAT: Due
to upcoming planned maintenance on the NPS 24/30 North Lateral Loop 2 (19699242),
service allowable for segments 6, 10, 11, 13, 14, 15, 16, 23, 24, and partial 28
(NEDA) will transition from 100% IT-D and 100% FT-D to 0% IT-D and 61% FT-D
effective September 22, 2025 at 08:00 MST until further notice.
Local Area/Location: N/A
New Information |
Updated Information |
Current and upcoming outages |
||||||
Outage ID |
Start |
End |
Facility/Outage Name |
Facility Type/Scope |
Outage Type |
Area of Impact |
19699242 |
Sep. 22, 2025 |
Sep. 29, 2025 |
NPS 24/30 North Lateral Loop 2 |
Pipeline
Maintenance |
Planned |
NEDA |
Upstream James River Area |
|||||
Effective: |
August
15, 2025 at 08:00 MST |
IT Allowable: 100% |
IT-R |
IT-S (receipt) |
|
Expected End: |
Until
further notice |
FT Allowable: 100% |
FT-R |
FT-P |
|
Interconnects: |
Aitken Creek, Big Eddy, Gordondale,
Groundbirch East, January Creek |
||||
Segments: |
West Gate Area |
||||||
Effective: |
June 02, 2025 at 08:00 MST |
IT Allowable:
100% |
IT-D |
|||
Expected End: |
Until
further notice |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
Interconnects: |
Alberta-B.C. Border and Alberta Montana
Border |
|||||
Segments: |
East
Gate Delivery Area |
||||||
Effective: |
August
01, 2025 at 08:00 MST |
IT
Allowable:
100% |
IT-D |
IT-S (delivery) |
||
Expected End: |
September 22, 2025
at 08:00 MST |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
Interconnects: |
Aeco C, Carbon,
Chancellor, Cold Lake, Crossfield East #2, Severn Creek, Empress, McNeil,
Unity, Warwick SE |
|||||
Segments: |
6, 10, 11, 13, 14,
15, 16, 17, 18, 19, 20, 23, 24, partial 21, and partial 28 (Greater EGAT) |
|||||
Effective: |
September 22, 2025
at 08:00 MST |
IT Allowable: 0% |
IT-D |
IT-S (delivery) |
||
Expected End: |
Until further notice |
FT Allowable: 61% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
Interconnects: |
Cold Lake, Unity, Warwick SE |
|||||
Segments: |
Local Area/Location |
N/A |
If there is an overlap
between Local Area/Location and Upstream James River Receipt Area, West Gate
Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT
Allowable will be in effect. The details in this bulletin supersede any
previously published information and will be reflected and maintained in the
next release of the Daily Operating Plan.
Capacity Constraint
Effective Start Date Time
09/17/2025 10:22 pm
Subject
NGTL Service (NEDA FT-D)
Notice Text
NGTL Service (NEDA FT-D)
USJR: N/A
WGAT: N/A
EGAT: Due
to upcoming planned maintenance on the NPS 24/30 North Lateral Loop 2 (19699242),
service allowable for segments 6, 10, 11, 13, 14, 15, 16, 23, 24, and partial 28
(NEDA) will transition from 100% IT-D and 100% FT-D to 0% IT-D and 61% FT-D
effective September 22, 2025 at 08:00 MST until further notice.
Local Area/Location: N/A
New Information |
Updated Information |
Current and upcoming outages |
||||||
Outage ID |
Start |
End |
Facility/Outage Name |
Facility Type/Scope |
Outage Type |
Area of Impact |
19699242 |
Sep. 22, 2025 |
Sep. 29, 2025 |
NPS 24/30 North Lateral Loop 2 |
Pipeline
Maintenance |
Planned |
NEDA |
Upstream James River Area |
|||||
Effective: |
August
15, 2025 at 08:00 MST |
IT Allowable: 100% |
IT-R |
IT-S (receipt) |
|
Expected End: |
Until
further notice |
FT Allowable: 100% |
FT-R |
FT-P |
|
Interconnects: |
Aitken Creek, Big Eddy, Gordondale,
Groundbirch East, January Creek |
||||
Segments: |
West Gate Area |
||||||
Effective: |
June 02, 2025 at 08:00 MST |
IT Allowable:
100% |
IT-D |
|||
Expected End: |
Until
further notice |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
Interconnects: |
Alberta-B.C. Border and Alberta Montana
Border |
|||||
Segments: |
East
Gate Delivery Area |
||||||
Effective: |
August
01, 2025 at 08:00 MST |
IT
Allowable:
100% |
IT-D |
IT-S (delivery) |
||
Expected End: |
September 22, 2025
at 08:00 MST |
FT Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
Interconnects: |
Aeco C, Carbon,
Chancellor, Cold Lake, Crossfield East #2, Severn Creek, Empress, McNeil,
Unity, Warwick SE |
|||||
Segments: |
6, 10, 11, 13, 14,
15, 16, 17, 18, 19, 20, 23, 24, partial 21, and partial 28 (Greater EGAT) |
|||||
Effective: |
September 22, 2025
at 08:00 MST |
IT Allowable: 0% |
IT-D |
IT-S (delivery) |
||
Expected End: |
Until further notice |
FT Allowable: 61% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
Interconnects: |
Cold Lake, Unity, Warwick SE |
|||||
Segments: |
Local Area/Location |
N/A |
If there is an overlap
between Local Area/Location and Upstream James River Receipt Area, West Gate
Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT
Allowable will be in effect. The details in this bulletin supersede any
previously published information and will be reflected and maintained in the
next release of the Daily Operating Plan.