TSP Name: EUREKA
8/6/2025 8:37 PM
Page 1 of 1
TSP Name / TSP:
EUREKA
Post Date/Time:
04-10-2025 02:50:00 PM
Subject:
Cain Ridge Compressor Station Maintenance [04-22-25] UPDATE
Notice Type:
CRITICAL
Notice ID:
40827
Prior Notice ID:
40626
Notice Status Description:
Supersede
Critical Notice Description:
Critical Notice
Notice Effective Date:
04-10-2025
Notice Effective Time:
02:50:00 PM
Notice End Date:
07-31-2025
Notice End Time:
12:00:00 AM
Required Response Indicator Description:
Notice Text:
Update to Notice ID #40626
Eureka Midstream LLC is providing notice that the duration for the planned maintenance scheduled for April 22, 2025, at Cain Ridge
Compressor Station has been changed to now impact the April 22 and 23, 2025, Gas Days.
Original Notice (Revised)
Eureka Midstream LLC is providing notice that planned maintenance has been scheduled at the Cain Ridge Compressor Station impacting the
April 22 and 23, 2025, Gas Days.
In conjunction with this maintenance, Compressor Station Capacity will be limited to 85,000 DTHS on the April 22 and 23, 2025, Gas Days.
Additionally, impacted parties with flowing production upstream of the Cain Ridge Compressor Station may experience higher than usual
operating pressures. Producers should adjust volumes to not exceed the aforementioned station capacities.
Nominations to delivery points in the Eureka Lean System should be adjusted accordingly by parties that flow through Cain Ridge Compressor
Station for the April 22 and 23, 2025, Gas Days.
Should specific shut ins be required, Eureka Midstream LLC will notify impacted parties.
Customers should monitor EQM Midstream Partners, LP – Gathering Informational Postings Website for updates to this notice.
*For production operations, Cain Ridge Compressor Station throughput will be reduced to 83 MMCFD for the April 22 and 23, 2025, Gas Days.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.
TSP Name: EUREKA
TSP Name / TSP:
EUREKA
Post Date/Time:
04-10-2025 02:50:00 PM
Subject:
Cain Ridge Compressor Station Maintenance [04-22-25] UPDATE
Notice Type:
CRITICAL
Notice ID:
40827
Prior Notice ID:
40626
Notice Status Description:
Supersede
Critical Notice Description:
Critical Notice
Notice Effective Date:
04-10-2025
Notice Effective Time:
02:50:00 PM
Notice End Date:
07-31-2025
Notice End Time:
12:00:00 AM
Required Response Indicator Description:
Notice Text:
Update to Notice ID #40626
Eureka Midstream LLC is providing notice that the duration for the planned maintenance scheduled for April 22, 2025, at Cain Ridge
Compressor Station has been changed to now impact the April 22 and 23, 2025, Gas Days.
Original Notice (Revised)
Eureka Midstream LLC is providing notice that planned maintenance has been scheduled at the Cain Ridge Compressor Station impacting the
April 22 and 23, 2025, Gas Days.
In conjunction with this maintenance, Compressor Station Capacity will be limited to 85,000 DTHS on the April 22 and 23, 2025, Gas Days.
Additionally, impacted parties with flowing production upstream of the Cain Ridge Compressor Station may experience higher than usual
operating pressures. Producers should adjust volumes to not exceed the aforementioned station capacities.
Nominations to delivery points in the Eureka Lean System should be adjusted accordingly by parties that flow through Cain Ridge Compressor
Station for the April 22 and 23, 2025, Gas Days.
Should specific shut ins be required, Eureka Midstream LLC will notify impacted parties.
Customers should monitor EQM Midstream Partners, LP – Gathering Informational Postings Website for updates to this notice.
*For production operations, Cain Ridge Compressor Station throughput will be reduced to 83 MMCFD for the April 22 and 23, 2025, Gas Days.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.