Equitrans Gathering Notice 41726
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
System Wide Notice Detail
TSP Name: EUREKA
8/6/2025 8:47 PM
Page 1 of 1
TSP Name / TSP:
EUREKA
Post Date/Time:
05-23-2025 08:25:00 AM
Subject:
Carbide Compressor Station Planned Maintenance (High Pressure) (06.26.2025)
Notice Type:
CRITICAL
Notice ID:
41726
Notice Status Description:
Initiate
Critical Notice Description:
Critical Notice
Notice Effective Date:
05-23-2025
Notice Effective Time:
08:25:00 AM
Notice End Date:
08-31-2025
Notice End Time:
12:00:00 AM
Required Response Indicator Description:
Notice Text:
Eureka Midstream LLC is providing notice that maintenance is scheduled at the Carbide Compressor Station (High Pressure) on Thursday June
26, 2025.
For Thursday June 26, 2025, Gas Day shippers flowing gas into the Eureka Rich pipeline system and delivering it to Mark West (Mobley), flow at
the Carbide Compressor Station (High Pressure) will be reduced to a maximum throughput of 180,000 DTH’s.
These reductions are based on current nomination levels, pipeline conditions and are subject to change.
Supply from the following (Low Pressure) meters will not be impacted by this reduction in Schedule Quantities: M1000602, M1000801,
M1000501, M1001301, M1000701, and M1001401.
Customers should monitor Equitrans’ Informational Postings website for updates to this notice.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.
TSP Name: EUREKA
TSP Name / TSP:
EUREKA
Post Date/Time:
05-23-2025 08:25:00 AM
Subject:
Carbide Compressor Station Planned Maintenance (High Pressure) (06.26.2025)
Notice Type:
CRITICAL
Notice ID:
41726
Notice Status Description:
Initiate
Critical Notice Description:
Critical Notice
Notice Effective Date:
05-23-2025
Notice Effective Time:
08:25:00 AM
Notice End Date:
08-31-2025
Notice End Time:
12:00:00 AM
Required Response Indicator Description:
Notice Text:
Eureka Midstream LLC is providing notice that maintenance is scheduled at the Carbide Compressor Station (High Pressure) on Thursday June
26, 2025.
For Thursday June 26, 2025, Gas Day shippers flowing gas into the Eureka Rich pipeline system and delivering it to Mark West (Mobley), flow at
the Carbide Compressor Station (High Pressure) will be reduced to a maximum throughput of 180,000 DTH’s.
These reductions are based on current nomination levels, pipeline conditions and are subject to change.
Supply from the following (Low Pressure) meters will not be impacted by this reduction in Schedule Quantities: M1000602, M1000801,
M1000501, M1001301, M1000701, and M1001401.
Customers should monitor Equitrans’ Informational Postings website for updates to this notice.