TSP Name: EUREKA
8/6/2025 8:55 PM
Page 1 of 1
TSP Name / TSP:
EUREKA
Post Date/Time:
06-19-2025 03:56:00 PM
Subject:
Carbide Compressor Station Capacity Constraint (High Pressure)(06.19.2025)
Notice Type:
CRITICAL
Notice ID:
42266
Notice Status Description:
Initiate
Critical Notice Description:
Critical Notice
Notice Effective Date:
06-19-2025
Notice Effective Time:
03:56:00 PM
Notice End Date:
09-30-2025
Notice End Time:
12:00:00 AM
Required Response Indicator Description:
Notice Text:
Eureka Midstream LLC is providing notice that there will be a Capacity Constraint at the Carbide Compressor Station (High Pressure) beginning
Thursday June 19, 2025, on the Intraday 2 cycle and until further notice.
Beginning Thursday June 19, 2025, Gas Day on the Intraday 2 cycle shippers flowing gas into the Eureka Rich pipeline system and delivering it
to Mark West (Mobley), flow at the Carbide Compressor Station (High Pressure) will be reduced to a maximum throughput of 250,000 DTH’s.
These reductions are based on current nomination levels, pipeline conditions, and are subject to change.
Supply from the following (Low Pressure) meters will not be impacted by this reduction in Schedule Quantities: M1000602, M1000801,
M1000501, M1001301, M1000701, and M1001401.
Customers should monitor Equitrans’ Informational Postings website for updates to this notice.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.
TSP Name: EUREKA
TSP Name / TSP:
EUREKA
Post Date/Time:
06-19-2025 03:56:00 PM
Subject:
Carbide Compressor Station Capacity Constraint (High Pressure)(06.19.2025)
Notice Type:
CRITICAL
Notice ID:
42266
Notice Status Description:
Initiate
Critical Notice Description:
Critical Notice
Notice Effective Date:
06-19-2025
Notice Effective Time:
03:56:00 PM
Notice End Date:
09-30-2025
Notice End Time:
12:00:00 AM
Required Response Indicator Description:
Notice Text:
Eureka Midstream LLC is providing notice that there will be a Capacity Constraint at the Carbide Compressor Station (High Pressure) beginning
Thursday June 19, 2025, on the Intraday 2 cycle and until further notice.
Beginning Thursday June 19, 2025, Gas Day on the Intraday 2 cycle shippers flowing gas into the Eureka Rich pipeline system and delivering it
to Mark West (Mobley), flow at the Carbide Compressor Station (High Pressure) will be reduced to a maximum throughput of 250,000 DTH’s.
These reductions are based on current nomination levels, pipeline conditions, and are subject to change.
Supply from the following (Low Pressure) meters will not be impacted by this reduction in Schedule Quantities: M1000602, M1000801,
M1000501, M1001301, M1000701, and M1001401.
Customers should monitor Equitrans’ Informational Postings website for updates to this notice.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.
8/6/2025 8:55 PM
Page 1 of 1