Adding proxy2: 8755 Equitrans Gathering Notice 43067 - API PipeRiv

Currently viewing the dev server.

Equitrans Gathering Notice 43067

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

System Wide Notice Detail

TSP Name: EUREKA

8/6/2025 9:05 PM

Page 1 of 1

TSP Name / TSP:

EUREKA

Post Date/Time:

07-28-2025 01:56:00 PM

Subject:

Carbide Compressor Station Capacity Constraint Update (High Pressure)(06.19.2025)

Notice Type:

CRITICAL

Notice ID:

43067

Prior Notice ID:

42266

Notice Status Description:

Supersede

Critical Notice Description:

Critical Notice

Notice Effective Date:

07-28-2025

Notice Effective Time:

01:56:00 PM

Notice End Date:

09-30-2025

Notice End Time:

12:00:00 AM

Required Response Indicator Description:

Notice Text:

Update to Notice ID #42266

Beginning Tuesday July 29, 2025, gas day, shippers flowing gas into the Eureka Rich pipeline system and delivering it to Mark West (Mobley),
flow at the Carbide Compressor Station (High Pressure) will be reduced to a maximum throughput of 270,000 DTH’s.

(Original Posting)

Eureka Midstream LLC is providing notice that there will be a Capacity Constraint at the Carbide Compressor Station (High Pressure) beginning
Thursday June 19, 2025, on the Intraday 2 cycle and until further notice.

Beginning Thursday June 19, 2025, Gas Day on the Intraday 2 cycle shippers flowing gas into the Eureka Rich pipeline system and delivering it
to Mark West (Mobley), flow at the Carbide Compressor Station (High Pressure) will be reduced to a maximum throughput of 250,000 DTH’s.

These reductions are based on current nomination levels, pipeline conditions, and are subject to change.

Supply from the following (Low Pressure) meters will not be impacted by this reduction in Schedule Quantities: M1000602, M1000801,
M1000501, M1001301, M1000701, and M1001401.

Customers should monitor Equitrans’ Informational Postings website for updates to this notice.

*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.

System Wide Notice Detail
TSP Name: EUREKA
TSP Name / TSP:
EUREKA
Post Date/Time:
07-28-2025 01:56:00 PM
Subject:
Carbide Compressor Station Capacity Constraint Update (High Pressure)(06.19.2025)
Notice Type:
CRITICAL
Notice ID:
43067
Prior Notice ID:
42266
Notice Status Description:
Supersede
Critical Notice Description:
Critical Notice
Notice Effective Date:
07-28-2025
Notice Effective Time:
01:56:00 PM
Notice End Date:
09-30-2025
Notice End Time:
12:00:00 AM
Required Response Indicator Description:
Notice Text:
Update to Notice ID #42266
Beginning Tuesday July 29, 2025, gas day, shippers flowing gas into the Eureka Rich pipeline system and delivering it to Mark West (Mobley),
flow at the Carbide Compressor Station (High Pressure) will be reduced to a maximum throughput of 270,000 DTH’s.
(Original Posting)
Eureka Midstream LLC is providing notice that there will be a Capacity Constraint at the Carbide Compressor Station (High Pressure) beginning
Thursday June 19, 2025, on the Intraday 2 cycle and until further notice.
Beginning Thursday June 19, 2025, Gas Day on the Intraday 2 cycle shippers flowing gas into the Eureka Rich pipeline system and delivering it
to Mark West (Mobley), flow at the Carbide Compressor Station (High Pressure) will be reduced to a maximum throughput of 250,000 DTH’s.
These reductions are based on current nomination levels, pipeline conditions, and are subject to change.
Supply from the following (Low Pressure) meters will not be impacted by this reduction in Schedule Quantities: M1000602, M1000801,
M1000501, M1001301, M1000701, and M1001401.
Customers should monitor Equitrans’ Informational Postings website for updates to this notice.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.
8/6/2025 9:05 PM
Page 1 of 1